Question # 41

Which statement about timeboxes is CORRECT?

Options:

A.  

Flow based working partitions work into timeboxes

B.  

A project cannot be referred to as a timebox

C.  

A timebox can contain another timebox

D.  

Timeboxes should be avoided in business as usual environments

Discussion 0
Question # 42

How are user inputs FIRST gathered in the 'quality' practice?

Options:

A.  

As user stories in the product backlog

B.  

As epic user stories in the project backlog

C.  

As the project Definition of Done in the quality management approach

D.  

As a quality control activity in the quality register

Discussion 0
Question # 43

What term is used to describe boards that display what work needs to be completed for people working on a project?

Options:

A.  

Work in progress limit

B.  

Information radiator

C.  

Highlight report

D.  

Glad! Sad! Mad!

Discussion 0
Question # 44

Which artifact identifies risks associated with using an iterative project management approach?

Options:

A.  

Project backlog

B.  

Agilometer

C.  

Risk management approach

D.  

Definition of Done

Discussion 0
Question # 45

Which of the following defines agility?

Options:

A.  

The set of activities that define the sequence of actions

B.  

The ability to embrace and respond to change

C.  

The ability to protect from uncontrolled changes

D.  

The core belief that anyone is capable of learning

Discussion 0
Question # 46

Which of the following integrated elements defines who is working on the project and who is affected by the project?

Options:

A.  

The project context

B.  

The PRINCE2 practices

C.  

The PRINCE2 processes

D.  

The “people” element

Discussion 0
Question # 47

Which statement about the ‘protect the level of quality’ target is CORRECT?

Options:

A.  

It is achieved by allowing enough time for testing

B.  

It is achieved by using the same team members

C.  

It gives confidence on the progress of the project

D.  

It delivers the early realization of benefits

Discussion 0
Question # 48

What should the business case state about the minimum viable product (MVP)?

Options:

A.  

When the MVP will be defined

B.  

That the MVP must go into operational use

C.  

What the MVP is

D.  

That the MVP is the same as project viability

Discussion 0

PRINCE2-Agile-Foundation PDF

PRINCE2-Agile-Foundation PDF (Printable)
$46.5
$154.99

PRINCE2-Agile-Foundation Testing Engine

PRINCE2-Agile-Foundation PDF (Printable)
$51
$169.99

PRINCE2-Agile-Foundation PDF + Testing Engine

PRINCE2-Agile-Foundation PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions