Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMBOK 7th Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 2 days ago
Total Questions : 2196

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 1

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.  

Planned all required training for the team during the onboarding process

B.  

Identified all required skills after the kick-off of the project

C.  

Identified all required skills during the planning of the project

D.  

Asked the sponsor to identify all required skills during the planning of the project

Discussion 0
Question # 2

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.  

Ask the team member to send their concerns in writing.

B.  

Empathize with the team member and discuss next steps.

C.  

Review the organization ' s human resources (HR) policy.

D.  

Schedule a meeting with the team member for the next work day.

Discussion 0
Question # 3

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager ' s priority in this situation?

Options:

A.  

Request that the team member gel the contract signed as soon as possible

B.  

Determine a mitigation strategy to move the project forward

C.  

Take over contract negotiations for the team member to speed up the process

D.  

Assist with the removal of impediments and blockers so that the project can continue

Discussion 0
Question # 4

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.  

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.  

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.  

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.  

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Discussion 0
Question # 5

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.  

Maintain a central repository of artifacts with a version control system.

B.  

Maintain separate document control via regions to avoid discrepancies.

C.  

Develop a document management software for version control.

D.  

Facilitate training on version control and project artifacts,

Discussion 0
Question # 6

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.  

Escalate the situation to the customer management team.

B.  

Ask the customer to discuss these changes with the product owner.

C.  

Request that the customer to meet with the team only at the weekly meeting.

D.  

Ask the customer to discuss these changes with the management team.

Discussion 0
Question # 7

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.  

Review the benefits management plan

B.  

Refer to the lessons learned from the first phase

C.  

Consult the project reports from the previous project manager

D.  

Collect information from related departments

Discussion 0
Question # 8

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation ' '

Options:

A.  

Instruct the team members involved to resolve the issue among themselves

B.  

Discuss the issue with the steering committee to determine the proper course of action.

C.  

Coordinate a video conference with the offending team member to resolve the issue

D.  

Reassign the offending team member to a different project

Discussion 0
Question # 9

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

Options:

A.  

Review the integrated change control process to restrict the number of changes

B.  

Focus on delivering incremental value through multiple smaller deliveries

C.  

Request sponsor support to get buy-in from the users and stakeholders

D.  

Restart the stakeholder engagement process by collecting user requirements again

Discussion 0
Question # 10

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.  

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.  

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.  

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.  

Determine what methods the team has been trained on and utilize those methods for the project.

Discussion 0
Question # 11

An organization is transitioning to an agile approach. At the project ' s first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.  

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.  

Ask the project team to address the product owner ' s issues since the product owner is responsible for the scope in agile.

C.  

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.  

Create a record in the issue register and escalate the issue to the project steering committee.

Discussion 0
Question # 12

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.  

Include enterprise environmental factors (EEFs)

B.  

Conduct a bottom-up estimate

C.  

Include projected inflation rates

D.  

Conduct an analogous estimate

Discussion 0
Question # 13

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

Options:

A.  

Share a template with the stakeholder to receive feedback on deliverables.

B.  

Ask the project sponsor to arrange a meeting with the stakeholder.

C.  

Use networking skills to approach the stakeholder.

D.  

Update the stakeholder engagement plan for the stakeholder.

Discussion 0
Question # 14

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Options:

A.  

Check the change management plan

B.  

Document the issue in the scope management plan.

C.  

Conduct a team brainstorming session to resolve the issue

D.  

Check the quality management plan

Discussion 0
Question # 15

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.  

Create an issue log template that will be used to identify and track impediments.

B.  

Create a contingency plan in case the project deviates from the initial plan.

C.  

Create a schedule management plan to ensure the project meets the delivery date.

D.  

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Discussion 0
Question # 16

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.  

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.  

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.  

Engage in a time and materials (T & M) contract and hire a local vendor to supportdevelopment.

D.  

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Discussion 0
Question # 17

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.  

Assess the business value impact and review the product roadmap to include any changes

B.  

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.  

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.  

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Discussion 0
Question # 18

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

Options:

A.  

The risk analysis was inadequate

B.  

The project was completed behind schedule

C.  

The requirements gathering was inadequate

D.  

The project was delivered above budget

Discussion 0
Question # 19

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.  

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.  

Propose an approach based on value measurement, such as the use of objectives and key results.

C.  

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.  

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Discussion 0
Question # 20

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

Options:

A.  

Seek help from experts to support the team member in fixing the problem.

B.  

Facilitate a session to reach an agreement with the team as a whole.

C.  

Negotiate with the customer a delay in the project delivery.

D.  

Accept the team ' s request to reassign the team member.

Discussion 0
Question # 21

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

Options:

A.  

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.  

Escalate the issue to the functional manager and ask for support.

C.  

Involve all stakeholders in the project by distributing status reports.

D.  

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.  

Engage all stakeholders in the project including the unsupportive stakeholders.

Discussion 0
Question # 22

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project

manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

Options:

A.  

Rectify ground rule violations.

B.  

Review performance formally.

C.  

Examine the team ' s virtual needs.

D.  

Implement new options.

Discussion 0
Question # 23

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.  

Provide a project management template for the project manager to follow as a guide.

B.  

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.  

Work with the project manager to develop a new approach that will bring benefits to the project.

D.  

Establish a project management methodology that requires the customer to provide daily updates to the team.

Discussion 0
Question # 24

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.  

Developing new product lines

B.  

Complying with new regulations

C.  

Establishing company processes

D.  

Certifying sustainable products

Discussion 0
Question # 25

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.  

Require a written status report from all team members on a weekly basis

B.  

Form a core group of team leads representing members from each country and encourage them to collaborate

C.  

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.  

Establish virtual one-on-one ' s with team members to address any issues and/or concerns privately

Discussion 0
Question # 26

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.  

Procure tools that consume less bandwidth for internet calls.

B.  

Record the meeting to share with the team members who were unable to join.

C.  

Ask the team members to use chat tools as an alternative to calls.

D.  

Determine what the problem is and develop an action plan.

Discussion 0
Question # 27

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.  

Allow team members to resolve personal issues without involving the project manager

B.  

Arrange and conduct team-building sessions to improve team effectiveness

C.  

Obtain feedback from the isolated team member to understand the situation

D.  

Get feedback from other team members to understand what led to this situation

E.  

Identify the isolated team member as a risk and document the situation in the risk register.

Discussion 0
Question # 28

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.  

Organize a brainstorming session with the project team to address the issue.

B.  

Advise the project team on the importance of team engagement,

C.  

Invest in coaching and training for all project team members.

D.  

Escalate the issue with the human resource (HR) department to take action,

Discussion 0
Question # 29

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.  

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.  

Engaged with the project sponsor to ensure support for the project manager ' s decision

C.  

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.  

Convinced the functional manager to stop the activities that will run beyond the budget

Discussion 0
Question # 30

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.  

Ask the team to focus on and deliver only the agreed-upon features.

B.  

Request additional budget because additional features are being added.

C.  

Encourage the team to continue, as this will eventually help the customer.

D.  

Ask the product owner to add the additional features to the requirements.

Discussion 0
Question # 31

A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.

Which action should the project manager take to address this situation?

Options:

A.  

Stop the project until the government transition has taken place.

B.  

Ask the sponsor to send a communication to the president-elect team with the progress of the project.

C.  

Ask the main stakeholders to document their progress on the project before the transition.

D.  

Accept the risk as these changes are part of the organizational culture.

Discussion 0
Question # 32

The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).

What should the project manager do?

Options:

A.  

Inform the stakeholders that the project goals are in the business case and change requests must be submitted.

B.  

Secure approval from the most influential stakeholders on the project goals and the needed functionality.

C.  

Host requirements gathering meetings where all of the stakeholders can identify their project goals until agreement is reached.

D.  

Develop a list of project goals, secure sponsor approval, and then socialize them with the direct and indirect stakeholders.

Discussion 0
Question # 33

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

Options:

A.  

Escalating a conflict within the project

B.  

Creating a new communication channel

C.  

Giving special attention to this stakeholder

D.  

Dismissing the stakeholder ' s opinions

Discussion 0
Question # 34

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

Options:

A.  

Set up regular project status meetings and invite all team members.

B.  

Encourage the team to define the ground rules for performance.

C.  

Set up individual calls to follow up on each team member ' s progress.

D.  

Invite team members to an informal meeting to get to know one another.

Discussion 0
Question # 35

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.

What should the project manager do first?

Options:

A.  

Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.

B.  

Meet with the operations manager to explain the background for the change and understand the operation manager ' s concerns about the change.

C.  

Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.

D.  

Formally acknowledge the operation manager ' s concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.

Discussion 0
Question # 36

A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?

Options:

A.  

Allocate additional resources to the development team to ensure the original scope can be completed on time.

B.  

Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

C.  

Agree on reducing the scope to match the team ' s resources and plan to add the removed items to future sprints.

D.  

Insist on keeping the original scope and explain the importance of meeting all the project milestones on time.

Discussion 0
Question # 37

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.  

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.  

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.  

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.  

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Discussion 0
Question # 38

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.  

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.  

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.  

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.  

Work with the team to understand their views and add the appropriate dependencies and risks.

Discussion 0
Question # 39

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

Options:

A.  

Have the team complete the technically complex story first.

B.  

Work with the product owner to clarify and prioritize the backlog stories.

C.  

Have the team complete the less complex story first.

D.  

Work with the agile coach on the user stories to avoid conflict.

Discussion 0
Question # 40

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

Options:

A.  

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.  

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.  

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.  

Reschedule the kick-off meeting for the following month so all can attend on-site.

Discussion 0
Question # 41

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Options:

A.  

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.  

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.  

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.  

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Discussion 0
Question # 42

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Options:

A.  

Ask the new team member to focus only on development and not do the testing.

B.  

Coach the new team member to conduct the testing the way it has always been done for this project.

C.  

Schedule a meeting with the new team member to learn about the new method of testing.

D.  

Request that the new team member do the testing the way it has always been done for this project.

Discussion 0
Question # 43

During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?

Options:

A.  

Ask the neighbor to leave the site immediately because the site is on private property.

B.  

Inform the neighbor that all of the project documentation has been approved.

C.  

Inform the neighbor that the complaint will be escalated to the project sponsor.

D.  

Ask the neighbor to submit a formal complaint about their concerns.

Discussion 0
Question # 44

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

Options:

A.  

Add more items to the sprint backlog that will add value.

B.  

Complete the sprint and seek a waiver from the regulator.

C.  

Complete the sprint, but do not release the deliverable.

D.  

Perform a sprint risk assessment and analyze challenges.

Discussion 0
Question # 45

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.  

Request that all team members receive the newest quality standards training and review one another ' s work.

B.  

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.  

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.  

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Discussion 0
Question # 46

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.  

Align the project goals with the team member.

B.  

Reassign the team member to another project.

C.  

Nominate the team member to receive agile training.

D.  

Allocate another resource to support the team member.

Discussion 0
Question # 47

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

Options:

A.  

Create a communications management plan.

B.  

Create a responsible, accountable, consulted, informed (RACI) chart.

C.  

Develop a kanban board.

D.  

Send a copy of the project charter to all project stakeholders.

Discussion 0
Question # 48

A project manager has been assigned to an existing infrastructure project. The current project manager, who is retiring, and the project sponsor have had a good working relationship for many years. The project sponsor has expressed dissatisfaction with having a new project manager assigned to the project.

What should the project manager do?

Options:

A.  

Set up a new communication plan and stakeholder engagement plan and submit to the project sponsor.

B.  

Discuss the strategic benefits of the project and schedule communication with the project sponsor.

C.  

Send weekly project reports to the project sponsor to provide an opportunity for engagement and feedback.

D.  

Set up a detailed meeting with the project sponsor and brief them about the project ' s progress.

Discussion 0
Question # 49

During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.

What should the project manager do?

Options:

A.  

Perform the change only if it has a higher or equivalent priority of the current remaining features.

B.  

Submit the feature changes to the change control board (CCB) so they can evaluate and approve.

C.  

Follow the plan by delivering the features and handle the change later in the project.

D.  

Discuss with the stakeholders about the possibility of accommodating the feature changes.

Discussion 0
Question # 50

Generative artificial intelligence (AI) now helps produce documents on most projects across an organization and is yielding great benefits. Despite this change, a project manager notices that very few members of their current team know the AI tools available within the company. Consequently, they do not know how to use them effectively.

What should the project manager do?

Options:

A.  

Identify more user-friendly generative AI applications in the industry and share with the team.

B.  

Engage with some experienced personnel in the company and request they mentor the rest of the team.

C.  

Document this issue as a lesson learned and hold a briefing at the end of the project.

D.  

Invite the project sponsor to brief the team on the importance of generative AI and how to optimize the available applications.

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions