Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMP) July 2026 Update is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMP) July 2026 Update

Last Update 2 days ago
Total Questions : 187

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 1

Acharity organization is considering adopting artificial intelligence (Al) technology to 100 secondary schools throughout the country. After completing a needs

assessment with the schools, the project manager realizes there is no internal expertise for such Al technology.

What should the project manager do next?

Options:

A.  

Identify value components with major stakeholders.

B.  

Prioritize the work with input from major stakeholders.

C.  

Propose outsourcing part of the project to a third-party supplier.

D.  

Hire a new senior project manager with domain knowledge for delivery.

Discussion 0
Question # 2

A new, highly innovative project just started and the customer is already complaining that the software company is not delivering as agreed. What should the project manager have done before starting the project?

Options:

A.  

Obtained the project statement of work (SOW) and client agreement sign-off.

B.  

Created a responsible, accountable, consulted, and informed (RACI) matrix.

C.  

Created a work breakdown structure (WBS) or epics-to-tasks hierarchy.

D.  

Evaluated the project ' s scope, size, risk, and other interdependencies.

Discussion 0
Question # 3

A team lead tells the project manager about a potential issue. Two project teams are working on parts of a project that are highly dependent on each other. The team

lead is concerned that this might create integration issues when the two teams ' outputs are combined.

What should the project manager do?

Options:

A.  

Set up periodic meetings between the teams to monitor each other ' s work and document issues.

B.  

Make a list of conflicts as they occur and assign a dedicated team resource to take corrective actions immediately.

C.  

Instruct both teams to continue working simultaneously, and address conflicts during the testing phase.

D.  

Identify which team ' s work should take precedence and then sequence the other team ' s work to avoid conflict.

Discussion 0
Question # 4

|

A project team is developing a product with monthly deliverables. The user feedback collected after each iteration affects how the product is developed further.

How should the project manager process the changes?

Options:

A.  

Assign the changes to the development team based on the feedback received.

B.  

Seek approval from the change control board (CCB) for the changes identified.

C.  

Analyze the impact on the schedule and cost due to the changes identified.

D.  

Incorporate the feedback into the backlog and work with the product owner for prioritization.

Discussion 0
Question # 5

A project manager is leading an iterative project to develop a very innovative product. However, a group of stakeholders are hesitant because the high complexity of the product involves many business rules.

What should the project manager do?

Options:

A.  

Seek advice from other project managers within the company and review their methods to build credibility.

B.  

Meet with the project team to devise a plan to build credibility.

C.  

Present another iterative project that has been completed by the project team recently to build credibility.

D.  

Ensure that project iterations deliver early wins to build credibility.

Discussion 0
Question # 6

A project manager is developing a project schedule in which only the high-level scope is defined; the detailed work breakdown structure (WBS) is to be developed at

the beginning of each project phase. Project teams are focusing on short-term objectives and can only detail the scope for work they are currently performing. Despite

this, the project sponsor asks for a master project schedule.

What two actions should the project manager take in this situation? (Choose 2)

Options:

A.  

Create a rough order of magnitude (ROM) schedule for the project activities with unclear scope, copying it from a previous project.

B.  

Switch the entire project to an agile approach, where the project management plan can be prepared in detail as the scope evolves with the project ' s progress.

C.  

) Tell the project sponsor that the master schedule cannot be completed since the complete details of the scope have not been discovered yet.

D.  

Tell the project team to go with the predictive approach and complete all the details of the project scope before starting any work.

E.  

Create a thorough schedule for the activities the team is currently working on and retain a high-level schedule for the remaining scope.

Discussion 0
Question # 7

A project manager has compared the monthly actual costs with the planned costs and estimated the forecast to complete the remaining part of the project. The project

manager realizes that the project will require additional funding.

What should the project manager do first?

Options:

A.  

Send the new cost estimates and ask the project sponsor to approve them.

B.  

Adjust the time and scope to keep the budget unchanged.

C.  

Ask the vendor to adjust the time and materials contract to reduce costs.

D.  

Assess the budget impact and submit a change request for approval.

Discussion 0
Question # 8

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.

During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.

Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.

The project manager leading the project to modernize health records in a hospital has a particular concern about clinical stakeholders—the doctors and nurses. As part of the stakeholder engagement plan, the project manager created the clinical advisory committee.

What was the objective of the project manager’s action?

(Refer to the Health Records Modernization at Hospital Case Study exhibit.)

Options:

A.  

To obtain early stakeholder buy-in and continuous feedback from key medical staff.

B.  

To document medical specifications to improve the technical elements of the process.

C.  

To reduce project overhead by engaging the medical staff in the execution process.

D.  

To comply with medical regulatory requirements by learning about them from the medical team.

Discussion 0
Question # 9

A project manager is leading a project for a new type of engine. When the project is in the design phase, the customer requests several new software requirements.

The development team, which is mainly focused on hardware design, is struggling to respond to the requests.

Which two actions should the project manager take? (Choose 2)

Options:

A.  

Report the current situation to the project sponsor, proposing to hire software specialists.

B.  

Send a formal letter to the human resources (HR) department to hire software specialists.

C.  

Ask the customer to modify the requirements so they could be solved using available resources.

D.  

Tell the customer that the development team is unable to meet their expectations of the software design.

E.  

Ask the acquisition team to consider contracting the service from an external vendor.

Discussion 0
Question # 10

A project manager notices that every time a new member joins the team, they spend too much time learning business terminology. This trend has impacted system

integrations and creates delays on a few tasks that other teams depend on.

What should the project manager do?

Options:

A.  

Ask the subject matter expert (SME) to organize their documentation in a centralized repository.

B.  

Ask the new team member to timebox the knowledge transfer to reduce the time spent with the team.

C.  

Ask the testing team to share their use case scenarios to familiarize the new team member.

D.  

Ask the new team member to research the terminology via the internet to avoid disruption.

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions