Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (2025 Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (2025 Version)

Last Update 2 days ago
Total Questions : 2040

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 1

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.  

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.  

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.  

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.  

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Discussion 0
Question # 2

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.  

Add resources to activities

B.  

Conduct serial activities on tasks

C.  

Increase the number of standup meetings

D.  

Perform tasks in parallel

Discussion 0
Question # 3

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.  

Verified applicable budget inputs related to this project

B.  

Assigned the same project resources to this project

C.  

Estimated a budget for the project's quality management

D.  

Determined a budget reserve for this project

Discussion 0
Question # 4

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.  

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.  

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.  

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.  

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Discussion 0
Question # 5

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.  

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.  

Check the ground rules of the meeting to review the initial agreement with the team members

C.  

Identify one team representative to speak up during the daily meeting and share the team updates

D.  

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Discussion 0
Question # 6

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.  

Consult preferred vendors from the company.

B.  

Perform research on experienced vendors in the market.

C.  

Source vendors with extensive experience.

D.  

Follow the company's standard vendor selection criteria process,

Discussion 0
Question # 7

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.  

Review the deliverable carefully and determine the right status

B.  

Assign one person to be responsible for the task

C.  

Establish a clear definition of done (DoD) for each task

D.  

Encourage team members to work together

Discussion 0
Question # 8

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.  

Confront the people causing the stress directly with the aim of finding amicable solutions

B.  

Seek support from the project management office (PMO) on addressing issues affecting the project

C.  

Discuss the possible actions with the project sponsor

D.  

Avoid the people causing stress and request a transfer as soon as possible

E.  

Talk to the human resources (HR) manager about these concerns

Discussion 0
Question # 9

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

Options:

A.  

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.  

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.  

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.  

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Discussion 0
Question # 10

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.  

Discuss the vacation plan and include scheduling changes in the change log database.

B.  

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.  

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.  

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Discussion 0
Question # 11

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.  

Review the iteration backlog because the product definition has changed and needs tobe reassessed before continuing the project.

B.  

Continue work and ask the product owner to assess the changes and add/remove thestories as needed in the backlog.

C.  

Ask a business analyst to assess the changes and then add/remove the stories in thebacklog and prioritize them by business value.

D.  

Ask the product owner to add new changes to the bottom of the backlog in order tohandle the modifications as a change request.

Discussion 0
Question # 12

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.  

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.  

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.  

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.  

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Discussion 0
Question # 13

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.  

Support the team member by removing the blockers and impediments.

B.  

Allocate the blockers and impediments to the product owner to resolve.

C.  

Insist that the person who raised the blockers and impediments take ownership.

D.  

Add any blockers or impediments to the risk register,

Discussion 0
Question # 14

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.  

Ask the team to work on the complaint raised by the clients.

B.  

Escalate the issue raised by the clients to the project sponsor,

C.  

Develop a solution with the team to identify the inventory level.

D.  

Work with the team and the product owner to define the next steps.

Discussion 0
Question # 15

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

Options:

A.  

Risk register

B.  

Project schedule

C.  

Change request

D.  

Issue log

Discussion 0
Question # 16

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

Options:

A.  

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.  

Work with 50% of the people internally and contract the other 50% to an outside company.

C.  

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.  

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Discussion 0
Question # 17

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.  

Move the solution designer to another team.

B.  

Review the process that resulted in this situation.

C.  

Stop work until the design document is completed.

D.  

Ask the team to document the design.

Discussion 0
Question # 18

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.  

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.  

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.  

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.  

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Discussion 0
Question # 19

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.  

Advise the teams to follow the company’s existing project management approach.

B.  

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.  

Let a senior team member select the approach that is appropriate.

D.  

Insist the teams both follow either a predictive or agile approach.

Discussion 0
Question # 20

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.  

Use a third-party instant messaging tool.

B.  

Use a password-enabled audio/video product,

C.  

Use a popular social media platform.

D.  

Use a collaborative electronic whiteboard,

Discussion 0
Question # 21

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.  

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.  

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.  

Meet with the client and discuss the project deadlines

D.  

Seek approval for more time for rework and resolve the issue

Discussion 0
Question # 22

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.  

Allow the most senior team members to decide the time that works for the team.

B.  

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.  

Discuss the lack of dedication with the team member and their functional manager.

D.  

Remove the team member from the project team to be fair to the other members.

Discussion 0
Question # 23

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.  

Document the issues and extend the project delivery timeline.

B.  

Convene the steering committee and inform them of the impact to the project.

C.  

Prioritize the user stories with issues and have the team resolve them

D.  

Update the project management plan and risk management plan.

Discussion 0
Question # 24

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.  

Update the scope management plan to track the new government requirements.

B.  

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.  

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.  

Request a change through the change control process to manage the new cybersecurityrequirements.

Discussion 0
Question # 25

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Question # 25

Options:

Discussion 0
Question # 26

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.  

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.  

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.  

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.  

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Discussion 0
Question # 27

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.  

Create a change request to extend the project's duration and costs.

B.  

Provide feedback to the team using project performance evaluations.

C.  

Escalate the impact on the schedule to the project sponsor.

D.  

Include buffer time in the schedule to absorb future delays.

Discussion 0
Question # 28

A new solution is being deployed in countries A B and

C.  

This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

Options:

A.  

Accept the change request from country A and reschedule the deployment project for country

A.  

B.  

Take the request into account and ask the sponsor to inform countries B and C about the change

C.  

Ask country A to submit a change request that will be analyzed along with countries B and C

D.  

Refuse country As request as there is no time for the change as deployment has already begun

Discussion 0
Question # 29

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.  

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.  

Engaged with the project sponsor to ensure support for the project manager's decision

C.  

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.  

Convinced the functional manager to stop the activities that will run beyond the budget

Discussion 0
Question # 30

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.  

Escalate a schedule risk to the sponsor.

B.  

Conduct team-building exercises.

C.  

Stop the project and perform a team skill assessment.

D.  

Make sure that the team has a full understanding of the scope.

Discussion 0
Question # 31

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.  

Shared

B.  

Accepted

C.  

Enhanced

D.  

Exploited

Discussion 0
Question # 32

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

Options:

A.  

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.  

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.  

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.  

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

Discussion 0
Question # 33

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.  

Expedite the next phase to reduce slippage

B.  

Add more float to the overall project schedule

C.  

Request additional contingency from the sponsor.

D.  

Organize a root cause analysis (RCA) workshop.

Discussion 0
Question # 34

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Options:

A.  

Establish the project scope and set clear team objectives

B.  

Set performance standards and direction

C.  

Hold early kick-off meetings and regular weekly meetings

D.  

Select members for their skill or potential

Discussion 0
Question # 35

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Options:

A.  

Tell the owner that a rough order of magnitude will be provided.

B.  

Contact a subject matter expert (SME) for advice and consultation.

C.  

Call a meeting with the project team to identify the most appropriate approach.

D.  

Tell the owner that the task requires more time and expertise

Discussion 0
Question # 36

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.  

Propose using a compliance review board that will be responsible for approving allproduct features prior to their release to the public.

B.  

Liaison with the compliance group, making them responsible for understanding therequirements and keeping them prioritized in the backlog.

C.  

Meet with the compliance team and make sure that their requirements are covered in thedefinition of done (DoD) for each story.

D.  

Ensure that the peer review process also covers compliance requirements, creating asecond layer of security for the project.

Discussion 0
Question # 37

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.  

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.  

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.  

Plan for training on agile tools and techniques used in the defined hybrid methodologyfor consistent application by all team members.

D.  

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Discussion 0
Question # 38

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.  

Analyze stakeholder diversity in the community.

B.  

Assess the need to collaborate with the community

C.  

Analyze the need to negotiate with the community.

D.  

Assess the information requirements of the community

Discussion 0
Question # 39

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.  

Update the risk register in order to add the issue.

B.  

Review the issue log regarding the concern

C.  

Revise the benefits management plan

D.  

Assess the repository to check for inconsistencies.

Discussion 0
Question # 40

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.  

Revise the project schedule and inform the stakeholders regarding any delays

B.  

Revise the project estimates and meet with the project team to discuss delays

C.  

Review the management reserve to identify any costs associated with the delays

D.  

Review the contingency reserve to identify any delays to the project

Discussion 0
Question # 41

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.  

Share project documentation in a repository with exclusive access.

B.  

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.  

Send periodic emails to senior management with the latest project updates.

D.  

Keep project artifacts up-to-date and accessible to all stakeholders.

Discussion 0
Question # 42

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.  

Have a discussion with the sales team to find a solution to the issue

B.  

Validate the reason and add n as an issue m the issue log

C.  

Escalate the issue to the functional manager

D.  

Direct the sales team to speak with accounting to resolve the issue

Discussion 0
Question # 43

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.  

Confirmed that the communication was understood and solicited feedback from the team

B.  

Sent the roles and responsibilities matrix along with the project management plan

C.  

Discussed the roles with the managers to help explain them to their team members

D.  

Briefed each team member on their roles before sending the project management plan

Discussion 0
Question # 44

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.  

Inform the design team to ensure compliance during the product design phase

B.  

Inform the quality team that they need to ensure that the product is in compliance

C.  

Ensure that compliance is explicitly mentioned in the relevant requirements

D.  

Meet with the team and remind them of the compliance requirements

Discussion 0
Question # 45

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.  

Ask the team member to send their concerns in writing.

B.  

Empathize with the team member and discuss next steps.

C.  

Review the organization's human resources (HR) policy.

D.  

Schedule a meeting with the team member for the next work day.

Discussion 0
Question # 46

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.  

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.  

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.  

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.

D.  

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Discussion 0
Question # 47

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.  

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.  

Continue working with the predictive approach to deliver the value at the end of the project.

C.  

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.  

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Discussion 0
Question # 48

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.  

Keep the project focused and executed in silos for better outcomes.

B.  

Report the concern to the agile project management office (PMO),

C.  

Inform the product owner of the concern so that i can be addressed.

D.  

Open up to the team to work collaboratively to achieve the outcomes.

Discussion 0
Question # 49

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.  

Meet with all project stakeholders to identify how to implement the technology.

B.  

Identify the disagreement in the risk register and develop a contingency plan.

C.  

Update the project charter to align with the desires of the project sponsor.

D.  

Negotiate with the project sponsor to develop a mutually beneficial solution.

Discussion 0
Question # 50

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Question # 50

Options:

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions