PMP Practice Questions
Project Management Professional (PMP) July 2026 Update
Last Update 2 days ago
Total Questions : 187
Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.
Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.
During project implementation, the project manager is communicating information about changes only at the executive level. Many people within the organization are uncertain about the project ' s status. There are rumors about changes to the project and how they may affect work activities.
What should the project manager do?
Agroup of specialists with years of experience is temporarily joining a project team. The project manager has been eager for their help in the production of a key
deliverable.
How should the project manager effectively lead these experienced team members?
After finishing a project, the project manager organized a lessons learned meeting. What should the project manager do next?
A new technology has been released into the market. The project sponsor realizes that incorporating this new technology into the project will significantly improve the
final deliverable. The project manager informs the project sponsor that the internal resources have no working experience with the technology and its related activities,
What should the project sponsor do?
A project team is planning a university graduation ceremony. During a team meeting, a team member disagrees with the project manager on the prioritization of
project activities. The team member thinks that it would be more efficient to prioritize the sponsorship instead of preparing a budget since a budget template already
exists.
What should the project manager do?
A strategic project is nearing completion. The project manager discovers the project team is reluctant to prepare the knowledge transfer documentation to the relevant business department because they are being assigned to a new, urgent project.
What should the project manager do?
A project to upgrade high-voltage transmission lines, towers, and substations in a remote mountainous area is 50% complete at the end of April.

The risk manager has implemented risk responses and is projecting the probability and impact for the remainder of the project. At a monthly risk meeting, the risk manager presents the chart shown above.
What two conclusions can be determined from this chart? (Choose 2)
A project manager is leading a predictive project. The main stakeholders involved in the project complain that the weekly status report sent over email, is very
confusing and so they expect a weekly meeting to be arranged to understand the project status and to ask questions wherever needed.
Which two steps should the project manager take? (Choose 2)
A project team repeatedly misses delivery target dates for the main project releases because of new requests from the client. Client satisfaction is high, even though the project is behind schedule.
What should the project manager do?
A project team had been developing their deliverables on a 2-week sprint. The deliverables were tested and proven to be functional. However, during the sprint
review, they were rejected because they failed to meet the end-user requirements.
What actions should the project manager have done?
