Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMBOK 7th Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 2 days ago
Total Questions : 2196

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 401

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

Approved Work Package Cost Estimates: US$9,500

Contingency reserves: $500 %

Management reserves: 10% of contingency reserves

Percent complete of the project: 50%

Planned percent of the project: 40%

Actual costs of the project: US$4,500

What is accurate about the project status?

Options:

A.  

The actual work is 25% more than the planned work.

B.  

The project cost is 10% lower than planned.

C.  

The actual work is 25% less than the planned work.

D.  

The project cost is 10% higher than planned.

Discussion 0
Question # 402

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.  

Email all stakeholders with the objectives of the project and ask for feedback.

B.  

Wait for a date when all required attendees can be available onsite.

C.  

Run separate meetings to accommodate everyone ' s schedule.

D.  

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Discussion 0
Question # 403

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.  

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.  

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.  

Assessed the organization ' s culture, performed a suitability analysis, and determinedthe future state.

D.  

Hired a third-party agile delivery team to do the implementation.

Discussion 0
Question # 404

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?

Options:

A.  

Cost oriented

B.  

Deliverable oriented

C.  

Customer oriented

D.  

Team oriented

Discussion 0
Question # 405

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

Options:

A.  

Communicate this issue to the human resources department.

B.  

Provide additional training to the new hire.

C.  

Increase team cohesiveness by sharing information and experiences openly.

D.  

Update the issue log and define the mitigation strategy.

Discussion 0
Question # 406

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

Options:

A.  

Escalate the issue to the project sponsor and seek assistance.

B.  

Engage the project stakeholder and ensure all requirements are captured.

C.  

Review the stakeholder engagement plan and communication strategy.

D.  

Review the product requirements and update the stakeholder register.

Discussion 0
Question # 407

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

Options:

A.  

Escalate to the project steering committee.

B.  

Invite the finance department to the next project demo.

C.  

Review the project requirements.

D.  

Use the currently available resources.

Discussion 0
Question # 408

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor ' s request to not archive the project artifacts.

B.  

Consult with the project management office (PMO) for guidance on project artifacts.

C.  

Archive the project artifacts on the project manager ' s local computer for future reference.

D.  

Document the project sponsor ' s instructions as the archived project artifacts.

Discussion 0
Question # 409

A project team ' s performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.  

Focus on remediation not merely on correcting symptoms

B.  

Compare the team ' s performance against other project teams

C.  

Identify potential failure points based on the iteration workload

D.  

Motivate the team to perform better

Discussion 0
Question # 410

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team ' s productivity.

What should the project manager do next?

Options:

A.  

Review the iteration duration with the team.

B.  

Discuss the issue in the next retrospective.

C.  

Encourage the team to improve their performance.

D.  

Reduce the iteration backlog.

Discussion 0
Question # 411

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

Options:

A.  

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.  

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.  

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.  

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

Discussion 0
Question # 412

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization ' s upper management.

What should the project manager do first?

Options:

A.  

Review the benefits of the proposed changes in relation to the business case.

B.  

Assess the time overrun, and start implementation to avoid additional delays.

C.  

Request a provisional budget increase to avoid any budget overruns.

D.  

Motivate the team to avoid the frustration of working on a prolonged project.

Discussion 0
Question # 413

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Question # 413

Options:

Discussion 0
Question # 414

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer ' s organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

Options:

A.  

Distributed a detailed quality management plan to the key stakeholders.

B.  

Included the final report during the closing phase to ensure common understanding.

C.  

Identified key stakeholders and included all of them in project agreement discussions.

D.  

Performed project reporting according to the communications management plan.

Discussion 0
Question # 415

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.  

Contact the human resource (HR) department for a solution.

B.  

Speak with the key team member to clarify the situation.

C.  

Conduct a meeting with the team to deliberate on a decision.

D.  

Suspend the team member until further notice.

Discussion 0
Question # 416

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

Options:

A.  

Risk log

B.  

Change log

C.  

Backlog

D.  

Issue log

Discussion 0
Question # 417

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.  

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.  

Escalate the issue to the functional manager

C.  

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.  

Perform the quantitative risk analysis for the team member.

Discussion 0
Question # 418

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

Options:

A.  

Engage an external vendor to perform the design phase under an iterative approach.

B.  

Request that new team members familiar with iterative approaches be assigned to this project.

C.  

Update the project schedule to consider a daily standup as part of the project design phase.

D.  

Define the ground rules, responsibilities, and conflict management strategies.

Discussion 0
Question # 419

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor ' s request to not archive the project artifacts.

B.  

Document the project sponsor ' s instructions as the archived project artifacts.

C.  

Archive the project artifacts on the project manager ' s local computer for future reference

D.  

Consult with the project management office (PMO) for guidance on project artifacts.

Discussion 0
Question # 420

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.  

Discuss the issue with the project sponsor.

B.  

Review the resources required for the tasks on the critical path.

C.  

Review and update the risk management plan.

D.  

Allocate resources to develop the competencies of the other team members

Discussion 0
Question # 421

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern ' s mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.  

Convinced the critical resource to remain on the project.

B.  

Requested an experienced resource as a replacement

C.  

Allocated additional time for mentoring

D.  

Negotiated additional time to complete the project

Discussion 0
Question # 422

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

Options:

A.  

The communications management plan was not used by all stakeholders.

B.  

Organizational assets were not available to back the rationale.

C.  

Relative estimation by the team resulted in two estimates.

D.  

The use of the Monte Carlo method can result in different estimations.

Discussion 0
Question # 423

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Review the stakeholder engagement plan.

C.  

Update the issue log.

D.  

Neutralize the negative stakeholders.

Discussion 0
Question # 424

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.  

Analyzed the sponsor ' s communication requirements.

B.  

Confirmed that the portal is providing adequate information.

C.  

Verified that the project team is following the communications management plan.

D.  

Ensured the sponsor had the necessary skills to use the portal.

Discussion 0
Question # 425

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

Options:

A.  

Escalate the issues to the project sponsor.

B.  

Review the issues log to ensure the issues are captured.

C.  

Check the risk management plan to ensure there is a strategy to address the issues.

D.  

Ask the key stakeholders to discuss the issues with the project team.

Discussion 0
Question # 426

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager ' s former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.  

Create an entry in the impediment board and assign it.

B.  

Invite the project team to a swarming session to define a solution

C.  

Leverage the network of the former department and ask for help

D.  

Escalate the issue to the product owner to define the next steps

Discussion 0
Question # 427

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.  

Schedule a meeting with the previous project manager

B.  

Submit a change request to the change control board (CCB)

C.  

Schedule training for project team members

D.  

Conduct an earned value analysis (EVA)

Discussion 0
Question # 428

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member ' s concerns?

Options:

A.  

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.  

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.  

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.  

Provide direction to the team lead on how to resolve the issue with the team member directly.

Discussion 0
Question # 429

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.  

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.  

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.  

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder ' s final product.

D.  

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Discussion 0
Question # 430

Match the project situation on the left to the meeting on the right where the situation could occur.

Question # 430

Options:

Discussion 0
Question # 431

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.  

Work with the finance team to transition to incremental budgeting.

B.  

Request the finance team to allocate a budget based on historical data.

C.  

Provide the budget to the finance team for only the planned increments.

D.  

Extrapolate the budget based on the current cost performance index (CPI).

Discussion 0
Question # 432

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

Options:

A.  

Request to meet with the team member and ask that any issues be escalated separately.

B.  

Reprimand the team member and provide immediate coaching on goal alignment.

C.  

Proceed with defining the goals with the team members given the majority approval from the team.

D.  

Approach the team member with empathy and obtain agreement through collaboration.

Discussion 0
Question # 433

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

Options:

A.  

Have a one-on-one discussion with each team member to emphasize their individualtalents.

B.  

Document the behavior of the team members and highlight it during their performancereviews.

C.  

Identify the team members who are not participating and reprimand them.

D.  

Explain the benefits of the approach and the effects of positive psychology.

Discussion 0
Question # 434

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.  

Include the new requirement in the next iteration of the software without informing the sponsor.

B.  

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.  

Release the software as is and start a new project to deliver the new requirements.

D.  

Collect the requirements of the regulation and follow the change control process.

Discussion 0
Question # 435

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.  

Assign this member to facilitate the next meeting to ensure project team collaboration.

B.  

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.

C.  

Review and update the project ground rules to make meeting attendance mandatory.

D.  

Understand the reason for the team member ' s absence and encourage them to attend future meetings.

Discussion 0
Question # 436

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company ' s CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.  

Redefine the communications management plan

B.  

Develop an integrated change management plan

C.  

Document the risk in the project risk register

D.  

Review the scope defined in the project charter

Discussion 0
Question # 437

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.  

Update the risk register and implement the approved risk response plan for qualitydeviations.

B.  

Identify the resources that were responsible for the deliverable and request a teamdevelopment plan.

C.  

Update the issue log, identify the involved stakeholders, and assign resources to thecorrective actions.

D.  

Submit a change request to update the project quality requirements for the involvedproject deliverable.

Discussion 0
Question # 438

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder ' s current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

Options:

A.  

Regression analysis

B.  

Stakeholder analysis

C.  

Qualitative risk analysis

D.  

Decision tree analysis

Discussion 0
Question # 439

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.  

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.  

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.  

Advise the team not to engage in modifications unless it follows the proper change approval process

D.  

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Discussion 0
Question # 440

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

Options:

A.  

Send the project charter to all stakeholders for information.

B.  

Send an email to all stakeholders directing them to approach the project managerdirectly.

C.  

Review the stakeholder engagement plan and inform the stakeholders.

D.  

Review the change management plan and ask the change control board (CCB) to beinvolved.

Discussion 0
Question # 441

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.  

Issue log

B.  

Lessons learned register

C.  

Stakeholder engagement plan

D.  

Risk register

Discussion 0
Question # 442

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.  

Include additional mitigation actions against feature defects and update the risk management plan.

B.  

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.  

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.  

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Discussion 0
Question # 443

A company ' s board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.  

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.  

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.  

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.  

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Discussion 0
Question # 444

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.  

Share the annual report with the sponsor.

B.  

Organize a stakeholder meeting to brainstorm on general project risks.

C.  

Extract this from the project risk register tracking tool and issues log.

D.  

Refer the sponsor to the contract document.

Discussion 0
Question # 445

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Options:

A.  

Request a performance assessment for the team from the functional manager.

B.  

Evaluate the current effectiveness of the team and define development needs.

C.  

Allow each team member to use their individual strengths for project success.

D.  

Assign team member roles and responsibilities based on past experience.

Discussion 0
Question # 446

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.  

Send an email update to existing team members about the addition of the new teammembers.

B.  

Set up a weekly meeting with the new team members for a couple of months.

C.  

Request the transfer of the new members to another project, citing a risk of confusion.

D.  

Update and share the guideline document dealing with team communication.

Discussion 0
Question # 447

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.  

The project should have constructed training centers in the remote towns.

B.  

The project did not identify and engage the correct stakeholders.

C.  

The project should have representatives in all the remote towns.

D.  

The project did not fully engage the project sponsor.

Discussion 0
Question # 448

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.  

Escalate the issue to the team member ' s functional manager and request a responseas soon as possible.

B.  

Meet with the team member to understand what the issues are and to provide support.

C.  

Leverage other team members who are contributing and making the project a success.

D.  

Have the team member transferred to another project and add other resources to theproject.

Discussion 0
Question # 449

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.  

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.  

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.  

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.  

Communicate to the affected team members ' manager and schedule a meeting to discuss the details of this assignment

Discussion 0
Question # 450

A project manager has recently joined a small company. The company ' s chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.  

Notify all team members that all steps in the process must be completed.

B.  

Escalate the issue to the other executive leadership members.

C.  

Schedule a review of the process steps with the team and the COO.

D.  

Redesign the process so the team can move more quickly.

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions