Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMBOK 7th Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 2 days ago
Total Questions : 2196

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 501

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

Options:

A.  

Refer to the stakeholder engagement plan.

B.  

Set up a conference call for all stakeholders.

C.  

Refer to the communications management plan.

D.  

Send an email to all stakeholders.

Discussion 0
Question # 502

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

Options:

A.  

Meet with the stakeholder to discuss the impact of the deliverable

B.  

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.  

Improve communication with the stakeholder to obtain their assistance in the future

D.  

Escalate to the project sponsor due to the political nature of the issue

Discussion 0
Question # 503

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.  

Plan to execute the procurement tasks in a virtual environment.

B.  

Review organizational process assets (OPAs) for similar projects.

C.  

Create a change request to extend the duration of the project.

D.  

Ask the project sponsor to put the project on hold.

Discussion 0
Question # 504

A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities

What should the project manager do next?

Options:

A.  

Document the project management plans and share them with the company and all team members via email for review

B.  

Create a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders

C.  

Add contingency m the schedule to account for dependencies and risks then review rt with the team

D.  

Engage with the company and the project team to determine the best course of action

Discussion 0
Question # 505

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor ' s bid?

Options:

A.  

US$650,000

B.  

US$452,500

C.  

US$547,500

D.  

US$582,500

Discussion 0
Question # 506

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.  

Perform stakeholder engagement with the virtual team

B.  

Add status reports to the communications management plan

C.  

Convene an on-site meeting for both of the teams

D.  

Add status report creation as a product backlog item

Discussion 0
Question # 507

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.  

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.  

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.  

Replace the key team members with new resources who are already aware of the agilemindset.

D.  

Provide directions to the team members on how to accelerate the company ' stransformation, bringing the project back on track.

Discussion 0
Question # 508

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.  

Manage the scope baseline to influence the factors that drive change.

B.  

Follow the proper change control process and evaluate the change for further impact.

C.  

Work with the customer to ensure the feature adds value.

D.  

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Discussion 0
Question # 509

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.  

Assess the impact of the features and refer it to the change control board (CCB).

B.  

Implement the new features after assessing the impact.

C.  

Reject the new features since it amounts to gold plating.

D.  

Add the new features to avoid losing the sponsor ' s support for the project.

Discussion 0
Question # 510

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.  

Become a servant leader by supporting team collaboration and removing impediments

B.  

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.  

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.  

introduce new communication tools to the project team members

Discussion 0
Question # 511

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

Options:

A.  

Identify the problem ' s root causes and define the ground rules with all project team members to minimize interferences.

B.  

Recommend to the project team members that they should improve their planning and make their stories smaller.

C.  

Reunite with the project team members affected and tell them not to reduce the team ' s capacity.

D.  

Hire a coach to help all project teams to improve their abilities to solve problems on their own.

Discussion 0
Question # 512

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project ' s

performance?

Options:

A.  

Results of the MoSCoW assessment

B.  

Cost-benefit analysis

C.  

Return on investment (ROI) analysis

D.  

Earned value analysis (EVA)

Discussion 0
Question # 513

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project ' s cost and schedule.

What should the project manager do first?

Options:

A.  

Perform an impact analysis with subject matter experts (SMEs).

B.  

Inform the government representative about the impact of the separate project.

C.  

Implement a change request to increase the budget and schedule.

D.  

Consult and update the risk register with the project stakeholders.

Discussion 0
Question # 514

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.  

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.  

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.  

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.  

Meet with the team member and search for the root cause of their behavior.

Discussion 0
Question # 515

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

Options:

A.  

Organizational process assets (OPAs)

B.  

Lesson learned registers from past projects

C.  

Historical issue logs

D.  

Project scope statement

E.  

Project management plan

Discussion 0
Question # 516

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A ' s project manager do?

Options:

A.  

Allow project B ' s leader to continue building relationships.

B.  

Talk with project B ' s leader to discuss possible impacts to both projects.

C.  

Tell project A ' s team member to ignore project B ' s leader.

D.  

Ensure project A ' s team member can finish the work committed to project

A.  

Discussion 0
Question # 517

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.  

Review the backlog to reschedule the deliverable for a later iteration.

B.  

Engage with stakeholders directly to review the iteration process.

C.  

Determine whether other cross-functional team members are able to take over thework.

D.  

Go to management and ask to hire a new external developer.

Discussion 0
Question # 518

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

Options:

A.  

Updated the stakeholder engagement plan to reflect a change in the product owner

B.  

Communicated the status of the project more frequently with the product owner

C.  

Updated the communications management plan to reflect a change in the communication needs

D.  

Reevaluated the new product owner ' s needs for better engagement

Discussion 0
Question # 519

A project manager is working with a customer ' s team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

Options:

A.  

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.  

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.  

A hybrid approach will allow the project manager to revise the product specifications.

D.  

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Discussion 0
Question # 520

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.  

Ask one of the more experienced team members to support the team member with the task.

B.  

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.  

Ask the experienced team members to produce a manual on how to complete the task.

D.  

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Discussion 0
Question # 521

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.  

Understand the customer ' s perspective and provide mentoring on agile mindsets.

B.  

Call for an internal team retrospective and create an improvement action plan.

C.  

Ask the customer to work with the product owner to prioritize all requests.

D.  

Work with the team to receive customer directions and improve the process.

Discussion 0
Question # 522

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

Options:

A.  

Assess and prioritize the impact of the new law on the project plan.

B.  

Update the project plan because the law is an obligation for the project.

C.  

Minimize the scope to catch the cost and schedule baseline.

D.  

Meet the sponsor to ask for additional time and budget increase.

Discussion 0
Question # 523

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

Options:

A.  

Prioritize the projects, giving higher priority to projects that will increase profit.

B.  

Make sure the project is fast tracked so that slipped time lines are recovered.

C.  

Request that upper management hire additional staff to support the projects.

D.  

Ensure that all of the projects are of high quality and are delivered on time.

Discussion 0
Question # 524

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.  

Lessons learned database

B.  

Procurement strategy

C.  

Vendor ' s website

D.  

Appropriate financial regulations

Discussion 0
Question # 525

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.  

Explain to the stakeholder that any modifications require additional budget

B.  

Review the missed program deliverables with the project team

C.  

Review the project charter for the project approval criteria

D.  

Speak with the team ' s manager to get extra hours from the team

Discussion 0
Question # 526

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

Options:

A.  

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.  

Update the acceptance criteria documentation to clearly reflect what was approved.

C.  

Review the new requirement and update all the stakeholders accordingly.

D.  

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Discussion 0
Question # 527

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Question # 527

Options:

Discussion 0
Question # 528

An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.

What should the project manager do next?

Options:

A.  

Discuss the issue with the management team.

B.  

Engage the project stakeholders.

C.  

Update the contract with a lower rate,

D.  

Engage the procurement team.

Discussion 0
Question # 529

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product ' s vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.  

Keep the project focused and executed in silos for better outcomes.

B.  

Report the concern to the agile project management office (PMO),

C.  

Inform the product owner of the concern so that i can be addressed.

D.  

Open up to the team to work collaboratively to achieve the outcomes.

Discussion 0
Question # 530

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.  

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.  

Continue working with the predictive approach to deliver the value at the end of the project.

C.  

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.  

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Discussion 0
Question # 531

A new solution is being deployed in countries A B and

C.  

This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

Options:

A.  

Accept the change request from country A and reschedule the deployment project for country

A.  

B.  

Take the request into account and ask the sponsor to inform countries B and C about the change

C.  

Ask country A to submit a change request that will be analyzed along with countries B and C

D.  

Refuse country As request as there is no time for the change as deployment has already begun

Discussion 0
Question # 532

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

Options:

A.  

Strive toward continuous improvement

B.  

Work together daily as a team

C.  

Only share suggestions at the end of the sprint

D.  

Follow the sprint planning

E.  

Send communications to the entire team

Discussion 0
Question # 533

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.  

Meet with each team member separately and apply an appropriate approach with each one.

B.  

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.  

Explain to the team that the project manager is ultimately responsible for the delivery.

D.  

Assign multiple managers to the various teams and delegate all of the tasks to them.

Discussion 0
Question # 534

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.  

Request for information

B.  

Scope statement

C.  

Issue log

D.  

Risk register

Discussion 0
Question # 535

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

Options:

A.  

Escalate the issue with an impediment to the project sponsor

B.  

Use the contingency budget to implement schedule compression

C.  

Implement the mitigation plans listed in the organizational process assets (OPAs)

D.  

Reassess the issue as part of monitoring and controlling

Discussion 0
Question # 536

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.  

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

B.  

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.  

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.  

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.

Discussion 0
Question # 537

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.  

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.  

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.  

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.  

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Discussion 0
Question # 538

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.  

Invite the client and product owner to all planning, review, and retrospective meetings.

B.  

Accept the escalations and manage them so the working relationship with the client isnot impacted.

C.  

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.

D.  

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.

Discussion 0
Question # 539

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.  

Plan the project based on the available resources and submit a change request upon completion.

B.  

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.  

Identify the technical requirements and request that management hire external resources,

D.  

Document the problem in the issue log and suggest a change request to decrease the scope.

Discussion 0
Question # 540

What should an agile lead do lo ensure their team is set up for success?

Options:

A.  

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.  

Schedule sprint meetings and coaching sessions to discuss project-related information

C.  

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.  

Document team tasks and challenges in order to understand when to step in and help a member of the team

Discussion 0
Question # 541

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country ' s economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do ' ?

Options:

A.  

Escalate the issue to the sponsor and ask for stakeholder engagement

B.  

Review the project business case and update it periodically

C.  

Plan for strategic program management

D.  

Implement a communications management plan

Discussion 0
Question # 542

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.  

Hire employees who specialize in agile approaches so they can better contribute toprojects.

B.  

Assign employees to agile projects so they can quickly adjust to the new approach.

C.  

Train all employees in agile approaches.

D.  

Shift the way the company views, reviews, and assesses employees.

Discussion 0
Question # 543

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.  

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.

B.  

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.

C.  

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.

D.  

Agree with the project team on a suitable collaboration and make sure information is shared at all times

Discussion 0
Question # 544

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager ' s supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.  

Send a formal communication regarding the missed milestone

B.  

Delay sending a formal communication until the project team catches up

C.  

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.  

Forego the formal communication and have a conversation with the supervisor

Discussion 0
Question # 545

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.  

Ask the team to work on the complaint raised by the clients.

B.  

Escalate the issue raised by the clients to the project sponsor,

C.  

Develop a solution with the team to identify the inventory level.

D.  

Work with the team and the product owner to define the next steps.

Discussion 0
Question # 546

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government ' s cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.  

Update the scope management plan to track the new government requirements.

B.  

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.  

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.  

Request a change through the change control process to manage the new cybersecurityrequirements.

Discussion 0
Question # 547

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.  

Review the project scope to align the project teams

B.  

Review the resource management plan to align the project teams

C.  

Review the project integration plan to align the project teams

D.  

Review the work breakdown structure (WBS) to align the project teams

Discussion 0
Question # 548

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

Options:

A.  

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.  

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.  

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.  

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

Discussion 0
Question # 549

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.  

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.  

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.  

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.  

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Discussion 0
Question # 550

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

Options:

A.  

Create a risk probability matrix to address the incompatibility.

B.  

identify an alternative component in case of incompatibility.

C.  

Use the contingency fund to redesign the interface if it is incompatible,

D.  

Require the vendor to redesign the incompatible component to fit the system.

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions