Free Certified Business Analysis Professional Practice Questions

Question # 11

Which of the following represents the duration of activities against a calendar?

Options:

A.  

Scatter chart

B.  

Gantt chart

C.  

Pie chart

D.  

Pareto chart

Discussion 0
Question # 12

Which of the following tasks cannot start until other tasks are completed?

Options:

A.  

Analysis task

B.  

Dependent task

C.  

Predecessor task

D.  

Independent task

Discussion 0
Question # 13

A team is working on a user privilege and access control system. A business analyst (BA) selects use cases as the technique for requirements specification.

What is the relationship between use cases "Create a role" and "Find a role" when there is a high level of formality?

Options:

A.  

Validate

B.  

Derive

C.  

Necessity

D.  

Satisfy

Discussion 0
Question # 14

There are 50 stakeholders in the current project. How many communication channels exist in this project?

Options:

A.  

1200

B.  

1225

C.  

1500

D.  

500

Discussion 0
Question # 15

Which of the following diagrams is used to display sensitivity analysis data?

Options:

A.  

Decision tree

B.  

Ishikawa

C.  

Influence

D.  

Tornado

Discussion 0
Question # 16

You are the business analyst for your organization and are working with Ralph who is also a business analyst at your company. You have moved one of the requirements higher in the prioritization of the requirements because it is needed to be implemented before some of the more important requirements are done. Ralph disagrees with your placement of the requirement because you are to rank the requirements based on their level of difficulty.

Who is correct and why?

Options:

A.  

Ralph is correct because the requirements are always to be ranked by importance or business value.

B.  

You are correct because the lower priority requirements must be completed before the higher priority requirements can be done.

C.  

You are correct because you are the senior business analyst.

D.  

Ralph is correct because the sequence of requirements is actually done with the project activity list.

Discussion 0
Question # 17

Which of the following is a narrative description of the work required for the project?

Options:

A.  

Contract work breakdown structure (CWBS)

B.  

Work breakdown structure (WBS)

C.  

Contract statement of work (CSOW)

D.  

Statement of work (SOW)

Discussion 0
Question # 18

Which of the following tasks does not rely on other activities, and no other activities rely on this task completing?

Options:

A.  

Analysis task

B.  

Independent task

C.  

Predecessor task

D.  

Dependent task

Discussion 0
Question # 19

Which of the following involves defining the various threats, determining the extent of vulnerabilities, and devising countermeasures against a possible attack?

Options:

A.  

Qualitative risk analysis

B.  

Risk analysis

C.  

Risk assessment

D.  

Quantitative risk analysis

Discussion 0
Question # 20

Which of the following requires that all parties in the conflict must give up something?

Options:

A.  

Barrier

B.  

Problem solving

C.  

Withdrawal

D.  

Compromising

Discussion 0

CBAP PDF

CBAP PDF (Printable)
$46.5
$154.99

CBAP Testing Engine

CBAP PDF (Printable)
$51
$169.99

CBAP PDF + Testing Engine

CBAP PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions