CEM Practice Questions

Certified Energy Manager (CEM)

Last Update 2 days ago
Total Questions : 130

Dive into our fully updated and stable CEM practice test platform, featuring all the latest Energy Management exam questions added this week. Our preparation tool is more than just a AEE study aid; it's a strategic advantage.

Our free Energy Management practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CEM. Use this test to pinpoint which areas you need to focus your study on.

CEM PDF

CEM PDF (Printable)
$43.75
$124.99

CEM Testing Engine

CEM PDF (Printable)
$50.75
$144.99

CEM PDF + Testing Engine

CEM PDF (Printable)
$63.7
$181.99
Question # 31

Which of the following best describes a dead band in controls?

Options:

A.  

A range around a set point with no change in state even though there is a change in sensor input

B.  

A system which changes the output of a controller based on how fast a variable is moving from or to a set point

C.  

The delay in response of a system to a controlled change

D.  

A value that has been assigned to a controlled variable

E.  

The difference between a sensor variable and its set point

Discussion 0
Question # 32

What is the definition of lamp life for a fluorescent lamp?

Options:

A.  

The time at which lamps begin to fail

B.  

The time at which 50% of a large sample of lamps have failed

C.  

The time at which 70% of a large sample of lamps have failed

D.  

The time at which lumen output has reduced by 50%

E.  

The time at which lumen output has reduced to 70% of the initial light output

Discussion 0
Question # 33

Which of the following statements best describe Demand Control Ventilation (DVC) in Building Automation Systems?

Options:

A.  

It satisfies indoor ventilation rates by preconditioning outdoor air with the exhaust air to decrease energy cost during cold, warm, or humid weather

B.  

It's a prescriptive procedure in which outdoor air intake rates are calculated based on the energy cost method that compares a proposed building design to a base annual energy cost design

C.  

It's a building standard for enclosed spaces in which biological, chemical, and physical contaminants are considered to meet thermal comfort requirements

D.  

It's an active evaluation of outdoor and indoor space conditions to determine the amount of thermal, mechanical and natural conditioning that is required

Discussion 0
Question # 34

What does a manometer measure?

Options:

A.  

Pressure

B.  

Volume

C.  

Distance

D.  

Voltage

Discussion 0
Question # 35

What is the best type of heat exchanger to recover and transfer latent heat energy from one air stream to another?

Options:

A.  

Heat pipe

B.  

Shell and tube

C.  

Ceramic recuperator

D.  

Desiccant heat wheel

E.  

Run-around system

Discussion 0
Question # 36

A cooling tower is delivering water to a chilled-water plant. The cooling tower outlet temperature has a 6°C approach temperature to the ambient air, wet-bulb temperature. The outside air conditions are 20°C dry bulb, 60% relative humidity. Using the psychrometric chart, at what temperature can the cooling tower deliver water to the chilled-water plant?

Options:

A.  

13°C

B.  

17°C

C.  

21°C

D.  

25°C

Discussion 0
Question # 37

What is a common method to reduce the impact of voltage imbalance?

Options:

A.  

Rebalance single-phase loads

B.  

Install harmonic filters

C.  

Install capacitors to improve power factor on three-phase loads

D.  

Reverse phase connections on three-phase motors

Discussion 0
Question # 38

A concentrating solar thermal system collects 5 GJ/h of thermal heat, which is delivered to a 94% efficient hot water generator. The hot water generator is used to raise the water temperature from 15°C to 65°

C.  

The specific heat of water (Cp) is 4.2 kJ/kg-°

C.  

What flow rate (liter/second) of hot water can be delivered from the hot water generator?

Options:

A.  

4.2 liter/second

B.  

6.2 liter/second

C.  

9.2 liter/second

D.  

12.0 liter/second

Discussion 0
Question # 39

An energy project implemented today saves $10,000 per year for the next 20 years. Using the 5% interest table, determine the total value of savings at the end of the 20th year?

Options:

A.  

$124,620

B.  

$146,907

C.  

$200,000

D.  

$330,660

E.  

$496,991

Discussion 0