Free Advanced HPE Edge-to-Cloud Solutions Written Exam Practice Questions

Question # 11

You are designing a solution for a customer that will support a virtualization workload based on HPE Synergy. Your customer has the following requirements:

    Dual-socket HPE Synergy compute nodes running ESXi 8.x with maximum memory supported

    Each node should have access to shared storage from HPE Alletra Storage MP B10000

    All virtual machines should be protected against host failure

    All virtual machines with vGPU must be protected with Fault Tolerance

    All compute nodes should boot from drives located in the D3940 Storage Modules protected with RAID 1

    All frames should be managed as one logical enclosure to simplify management

    All compute nodes should support two network ports with the maximum Ethernet connectivity speed

You are reviewing a proposal that you must verify. The proposal contains:

    3 HPE Synergy 12000 frames

    2 HPE Synergy Composer2 modules

    4 HPE Virtual Connect SE 100Gb F32 Modules for Synergy

    4 HPE Synergy 50Gb Interconnect Link Modules

    3 HPE Synergy D3940 Storage Modules, each with 20 SSD drives

    1152 core vSphere Enterprise Plus subscriptions

    36 HPE Synergy 480 Gen11 compute nodes

Each SY480 Gen11 is configured with:

    A single Platinum CPU with 32 cores

    HPE Synergy 6820C 25/50Gb Converged Network Adapter

    HPE Synergy 5830C 32Gb Fibre Channel Host Bus Adapter

    HPE MR416i-o Gen11 12G SAS Mezzanine Controller

Which two statements are true regarding the proposal? (Select two.)

Options:

A.  

2 HPE Synergy 50Gb Interconnect Link Modules should be removed from the proposal, as the total number of interconnects required is six.

B.  

HPE MR416i-o Smart RAID controller can be removed because there are no external SAS disk enclosures included in the proposal.

C.  

Two HPE Virtual Connect SE 100Gb F32 Modules for Synergy can be removed from the proposal because all requirements are met without them.

D.  

To access HPE Alletra MP B10000 arrays, FC upgrade licenses for HPE Virtual Connect SE 100Gb F32 Modules for Synergy must be purchased.

E.  

vSphere Enterprise Plus subscriptions can be replaced with vSphere Standard subscriptions.

Discussion 0
Question # 12

You are designing a solution for a customer that will support a virtualization workload based on HPE Synergy. Your customer has the following requirements:

    Dual-socket HPE Synergy compute nodes running ESXi 8.x with maximum memory supported

    Each node should have access to shared storage from HPE Alletra Storage MP B10000

    All virtual machines should be protected against host failure

    All virtual machines with vGPU must be protected with Fault Tolerance

    All compute nodes should boot from disks located in the D3940 Storage Modules protected with RAID 1

    All frames should be managed as one logical enclosure to simplify management

    All compute nodes should support two network ports with the maximum Ethernet connectivity speed

You are reviewing a proposal that you must verify. The proposal consists of:

    3 x HPE Synergy 12000 frames

    2 x HPE Synergy Composer2 modules

    4 x HPE Virtual Connect SE 100Gb F32 Modules for Synergy

    4 x HPE Synergy 50Gb Interconnect Link Modules

    3 x HPE Synergy D3940 Storage Modules, each with 20 SSD drives

    1152 core VMware vSphere Enterprise Plus subscriptions

    36 x HPE Synergy 480 Gen11 compute nodes

Each SY480 Gen11 is configured with:

    A single Platinum CPU with 32 cores

    HPE Synergy 6820C 25/50Gb Converged Network Adapter

    HPE Synergy 5830C 32Gb Fibre Channel Host Bus Adapter

    HPE MR416i-o Gen11 12G SAS Mezzanine Controller

Which two statements are true regarding the proposal? (Select two.)

Options:

A.  

2 HPE Synergy 50Gb Interconnect Link Modules should be removed from the proposal, as the total number of interconnects required is six.

B.  

HPE MR416i-o Smart RAID controller can be removed because there are no external SAS disk enclosures included in the proposal.

C.  

Two HPE Virtual Connect SE 100Gb F32 Modules for Synergy can be removed from the proposal because all requirements are met without them.

D.  

To access HPE Alletra MP B10000 arrays, FC upgrade licenses for HPE Virtual Connect SE 100Gb F32 Modules for Synergy must be purchased.

E.  

vSphere Enterprise Plus subscriptions can be replaced with vSphere Standard subscriptions.

Discussion 0
Question # 13

Your customer has a networking environment based on Aruba CX 8325 switches configured with Quality of Service settings that give higher priority to iSCSI traffic between HPE ProLiant servers and HPE Alletra 6000 storage. They are planning to add HPE Synergy frames with HPE Virtual Connect modules that will connect to the same Aruba infrastructure.

The frames will be deployed in different VLANs. They need to update their environment to provide a lossless fabric for RoCE traffic that will traverse between the HPE Synergy frames and through multiple switches.

Your customer has two sets of Synergy frames in different logical enclosures connected with Aruba CX 8325 switches. They want to update their environment to provide lossless traffic for RoCE traffic.

What is the correct environmental or design change that will meet the customer’s new requirement?

Options:

A.  

Use RoCEv1 and configure DCBX on the switch facing the CNA in the servers.

B.  

Server Profiles should include redundant connections to a RoCE network.

C.  

Create DCB queues using server’s operating system utility.

D.  

Assign two different priority values to RoCE traffic.

Discussion 0
Question # 14

You are designing an HPE solution for SAP HAN

A.  

You are considering an as-a-service approach as one of the variants to be proposed to the customer.

What is true regarding HPE GreenLake for SAP HANA?

Options:

A.  

HPE GreenLake for SAP HANA requires an onsite HPE Alletra Storage MP X10000.

B.  

HPE GreenLake for SAP HANA offers billing based on GB of RAM used by SAP HAN

A.  

C.  

HPE GreenLake for SAP HANA can be used for SAP HANA instances running in the public cloud.

D.  

HPE GreenLake for SAP HANA offers billing based on the amount of users using SAP HAN

A.  

Discussion 0
Question # 15

Your customer plans to replace a legacy HPE BladeSystem solution with the HPE Synergy platform.

The customer requirements include:

    30 compute nodes to support their virtualization workloads

    Redundancy within the management subsystem

    An in-frame storage solution to support vSAN

    A redundant networking subsystem with the ability to virtualize WWNs

    Simplified management with a single logical enclosure

You are reviewing the following proposal:

    3 x HPE Synergy 12000 frames

    2 x HPE Virtual Connect SE 100Gb F32 Modules for Synergy

    4 x HPE Synergy 50Gb Interconnect Link Modules

    3 x HPE D3940 Storage Modules with maximum number of drives

    6 x HPE Composer2 + 30 x HPE OneView Advanced licenses

    30 x SY 480 Gen11 compute modules, each with 2 CPUs and appropriate mezzanine cards

Which statement about this proposal is true to help meet the customer requirements?

Options:

A.  

Additional HPE OneView Advanced licenses should be added for the HPE Virtual Connect modules and HPE D3940 Storage Modules.

B.  

30 x HPE OneView Advanced licenses should be removed from the proposal.

C.  

HPE 32Gb switches should be added to the proposal to enable WWNs virtualization and profile mobility.

D.  

3 x HPE Composer2 modules can be removed from the proposal, as you need one HPE Composer2 module per HPE Synergy frame for enhanced availability.

Discussion 0

HPE7-V01 PDF

HPE7-V01 PDF (Printable)
$46.5
$154.99

HPE7-V01 Testing Engine

HPE7-V01 PDF (Printable)
$51
$169.99

HPE7-V01 PDF + Testing Engine

HPE7-V01 PDF (Printable)

Free Exams Sample Questions