Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free V6 ENOVIA V6 Program Central (V6R2012) Practice Questions

Exams4sure Dumps

Exam style questions across every ENOV612-PRG domain

Last Update 3 days ago
Total Questions : 138

Start with our free ENOV612-PRG practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real ENOVIA exam. Each ENOV612-PRG exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your Dassault Systemes weak domains, see where you're losing marks, and build a focused study plan in minutes.

ENOV612-PRG PDF

ENOV612-PRG PDF (Printable)
$54.25
$154.99

ENOV612-PRG Testing Engine

ENOV612-PRG PDF (Printable)
$59.5
$169.99

ENOV612-PRG PDF + Testing Engine

ENOV612-PRG PDF (Printable)
$74.55
$212.99
Question # 11

Int the following image, what does the dependency (FS) specify?

Question # 11

Options:

A.  

Import the points WBS task must finish before the Filter the points task can start

B.  

Import the points WBS task must start before the Filter the points task can finish

C.  

Import the points WBS task must finish before the Filter the points task can finish

D.  

Import the points WBS task must start before the Filter the points task can start

Discussion 0
Question # 12

When you copy a Project Template, what information is copied to the new template?

Options:

A.  

WBS, Questions, Folders

B.  

WBS, Folders, Assessments, Risks

C.  

WBS, Routes, Folders, Discussions

D.  

WBS, Routes, Risks

Discussion 0
Question # 13

What is a project?

Options:

A.  

A collection of tasks to be performed

B.  

Several tasks in a specific sequential order

C.  

Tasks bounded by time, resources and required results

D.  

All of these

Discussion 0
Question # 14

When creating a route, which route task action provides the following options: Approve, Comment, Investigate, Information Only and Notify Only?

Options:

A.  

Review

B.  

Approval

C.  

Standard

D.  

Scope

Discussion 0
Question # 15

In addition to tasks dependencies, how can you specify a delay between tasks?

Options:

A.  

with Slack Time in days or hours

B.  

with Start Delay time in days or hours

C.  

with Start-to-Start time in hours

D.  

None of these

Discussion 0
Question # 16

What folder permission will you need to be able to view, add and delete objects from the folder?

Options:

A.  

Remove

B.  

Add

C.  

Add Remove

D.  

Read Write

Discussion 0
Question # 17

Once a project budget has been promoted to Plan Frozen:

Options:

A.  

cost categories can still be added

B.  

benefits categories can still be added

C.  

Estimates and Actuals can be entered

D.  

no items ca be added

Discussion 0
Question # 18

Which of the following is NOT true about Effort Management?

Options:

A.  

Effort level is shown on the Project level and WBS task level

B.  

On the Project level, each task is shown with the number of days used for each assignee over each week

C.  

Effort is shown as the percentage of time a person is allocated to a specific WBS Task

D.  

The total effort accrued for all the people to complete the task is shown as a percentage

Discussion 0
Question # 19

If the Assignee of a Route Task is a Group then,

Options:

A.  

All members of the group must perform the task

B.  

One member of the group must accept and perform the task

C.  

The task cannot be delegated to members outside the group

D.  

Only group members that also have the role of Project Lead can perform the task

Discussion 0
Question # 20

When 2 people are assigned to the same task, the default allocation is that...

Options:

A.  

both are set to 100%

B.  

each one is set to 50%

C.  

the 1st assigned person is set to 100% and the 2nd to 0%

D.  

both are set to 0%

Discussion 0