Question # 41

The RJ-45 is now known as the 8P8C style connector, per the Telecommunications Industry Association (TIA) standard. What does the P and C stand for?

Options:

A.  

Plug and connector

B.  

Position and connector

C.  

Position and contact

D.  

Plug and contact

Discussion 0
Question # 42

The ability of a conductors insulation to transmit an electric field is called:

Options:

A.  

Conductivity

B.  

Transmitability

C.  

Permittivity

D.  

Capacitance

E.  

Reactance

Discussion 0
Question # 43

Which of the following is NOT a type of connector for optical fiber?

Options:

A.  

LC

B.  

ST

C.  

SFF

D.  

S/FTP

E.  

SC

Discussion 0
Question # 44

A furniture cluster with 26 requires a MINIMUM of how many multiuser telecommunications outlet assembly (MUTOA)?

Options:

A.  

1

B.  

2

C.  

3

D.  

4

E.  

5

Discussion 0
Question # 45

A telecommunications outlet/connector may be provided using all listed below EXCEPT:

Options:

A.  

Wireless AP connectivity

B.  

Balanced twisted-pair outlets

C.  

Optical fiber connectors

D.  

4p4c (4 position, 4 contact) connector

Discussion 0
Question # 46

What is the PERT estimate (in hours) for project design where:

- Optimistic time is 40 hours

- Most likely time is 50 hours

- Pessimistic time is 60 hours

Options:

A.  

40 hours

B.  

45 hours

C.  

50 hours

D.  

55 hours

E.  

60 hours

Discussion 0
Question # 47

All of the following are true about the post construction phase EXCEPT:

Options:

A.  

The owner is responsible to update the record copy drawings to reflect "as-built" documents.

B.  

The contractors are resolving issues identified on the punch lists.

C.  

The architect is involved in final acceptance and contract closeout activities.

D.  

The construction manager is coordinating removal of construction equipment and job trailers.

Discussion 0
Question # 48

At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?

Options:

A.  

The project is under budget.

B.  

The project is budget incorrect.

C.  

The project has been back-end loaded.

D.  

The project is over budget.

Discussion 0
Question # 49

You are reviewing a building backbone design with a vertically aligned telecommunications room (TR). In the spec you note in a footnote with details that the slots at one end of the telecommunications room (TR) must be flush with the floor and the sleeves provide at the end of the telecommunications room (TR) must also be flush. In your meeting with the electrical engineering firm that has provided the spec, you make the comment that according to best practices, the MINIMUM that slots and sleeves must extend above the finished floor are:

Options:

A.  

25 mm (1 in) for slots and 51 mm (2 in)

B.  

25 mm (1 in) for slots and 25 mm (1 in)

C.  

51 mm (2 in) for slots and 25 mm (1 in)

D.  

51 mm (2 in) for slots and 51 mm (2 in)

E.  

64 mm (2 1/2 in) for slots and 64 mm (2 1/2 in)

Discussion 0
Question # 50

The decision regarding the number of optical fibers to install (fiber strand count) in a backbone depends largely on all of the following EXCEPT:

Options:

A.  

Level of multiplexing

B.  

Intended end-user applications

C.  

Physical topology of the cabling system

D.  

Distance between telecommunications room (TR)

E.  

Cabling system configuration

Discussion 0

RCDD-002 PDF

RCDD-002 PDF (Printable)
$46.5
$154.99

RCDD-002 Testing Engine

RCDD-002 PDF (Printable)
$51
$169.99

RCDD-002 PDF + Testing Engine

RCDD-002 PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions