Certified Construction Manager (CCM)
Last Update 2 days ago
Total Questions : 65
Certified Construction Manager is stable now with all latest exam questions are added 2 days ago. Incorporating Construction-Manager practice exam questions into your study plan is more than just a preparation strategy.
Construction-Manager exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through Construction-Manager dumps allows you to practice pacing yourself, ensuring that you can complete all Certified Construction Manager practice test within the allotted time frame.
Which delivery method, if not properly coordinated, introduces the strong possibility of work scope being duplicated or even omitted?
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am–7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
Lifecycle analysis of a project will provide the greatest impact during which of the following phases?
What are the basic responsibilities of an Agency CM related to safety on a construction project?
During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider
A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner
The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
TESTED 19 Oct 2025
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.