Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Good News !!! Construction-Manager Certified Construction Manager (CCM) is now Stable and With Pass Result

Construction-Manager Practice Exam Questions and Answers

Certified Construction Manager (CCM)

Last Update 2 days ago
Total Questions : 65

Certified Construction Manager is stable now with all latest exam questions are added 2 days ago. Incorporating Construction-Manager practice exam questions into your study plan is more than just a preparation strategy.

Construction-Manager exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through Construction-Manager dumps allows you to practice pacing yourself, ensuring that you can complete all Certified Construction Manager practice test within the allotted time frame.

Construction-Manager PDF

Construction-Manager PDF (Printable)
$43.75
$124.99

Construction-Manager Testing Engine

Construction-Manager PDF (Printable)
$50.75
$144.99

Construction-Manager PDF + Testing Engine

Construction-Manager PDF (Printable)
$63.7
$181.99
Question # 1

Which delivery method, if not properly coordinated, introduces the strong possibility of work scope being duplicated or even omitted?

Options:

A.  

Design-Bid-Build (DBB)

B.  

Design Build (DB)

C.  

Multi-Prime

D.  

CM at Risk (CMAR)

Discussion 0
Question # 2

The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?

Options:

A.  

CM

B.  

Regulatory agencies

C.  

CxA

D.  

Designer

Discussion 0
Question # 3

A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am–7pm, 5 days per week and that the bridge would be completed by September 1.

The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.

The CM should

Options:

A.  

tell the contractor they have until September 1 and can only work 7am–7pm.

B.  

discuss with the owner and tell the contractor to do only 1/2 of the bridge.

C.  

meet with the owner and contractor to vet all issues/options and make a decision.

D.  

meet with the contractor to go over realistic time frames and make a decision.

Discussion 0
Question # 4

Lifecycle analysis of a project will provide the greatest impact during which of the following phases?

Options:

A.  

Pre-Design

B.  

Design

C.  

Construction

D.  

Procurement

Discussion 0
Question # 5

What are the basic responsibilities of an Agency CM related to safety on a construction project?

Options:

A.  

To oversee the safety of the construction contractor's personnel

B.  

To monitor the safety of the designer's personnel

C.  

To manage the safety of the construction contractor's personnel, the designer's personnel, and the Agency CM's personnel

D.  

To execute safety requirements that are spelled out by the Agency CM's contract with the owner and statutes/laws

Discussion 0
Question # 6

During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider

Options:

A.  

incorporating Time and Material Alternates into the bid documents.

B.  

incorporating Add/Deduct Alternates into the bid documents.

C.  

evaluating Phase Alternates in the bid documents.

D.  

evaluating Schedule Alternates in the bid documents.

Discussion 0
Question # 7

A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner

Options:

A.  

modify the CM contract to include safety management to protect the owner's interests.

B.  

provide a safety coordinator to perform the necessary project safety functions on behalf of the contractor.

C.  

have the contractor submit a safety management plan for review and approval by the owner.

D.  

ensure they have a contractor-controlled insurance program (CCIP) to cover the safety risk for the project.

Discussion 0
Question # 8

The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?

Options:

A.  

$270,000

B.  

$450,000

C.  

$1.2 million

D.  

$2.7 million

Discussion 0
Question # 9

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.  

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.  

Send the bid back to the contractor and apologize for the mishap.

C.  

Include the unopened bid. since it clearly was an oversight.

D.  

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Discussion 0
Question # 10

A CM's responsibility for safety on the jobsite includes

Options:

A.  

no obligation for safety as it is the contractor's responsibility.

B.  

a professional obligation shared with others.

C.  

certifying subcontractor compliance.

D.  

drafting the contractor's safety plan.

Discussion 0
Get Construction-Manager dumps and pass your exam in 24 hours!

Free Exams Sample Questions