Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

ISO-21502-Lead-Project-Manager PECB ISO 21502 Lead Project Manager Exam is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

ISO-21502-Lead-Project-Manager Practice Questions

PECB ISO 21502 Lead Project Manager Exam

Last Update 3 days ago
Total Questions : 80

Dive into our fully updated and stable ISO-21502-Lead-Project-Manager practice test platform, featuring all the latest ISO 21502 exam questions added this week. Our preparation tool is more than just a PECB study aid; it's a strategic advantage.

Our free ISO 21502 practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about ISO-21502-Lead-Project-Manager. Use this test to pinpoint which areas you need to focus your study on.

ISO-21502-Lead-Project-Manager PDF

ISO-21502-Lead-Project-Manager PDF (Printable)
$54.25
$154.99

ISO-21502-Lead-Project-Manager Testing Engine

ISO-21502-Lead-Project-Manager PDF (Printable)
$59.5
$169.99

ISO-21502-Lead-Project-Manager PDF + Testing Engine

ISO-21502-Lead-Project-Manager PDF (Printable)
$74.55
$212.99
Question # 11

According to ISO 21502, what is the main purpose of pre-project activities?

Options:

A.  

To evaluate the competence of project team members

B.  

To ensure that the project work will be undertaken in a timely manner

C.  

To verify if the project is worth starting

Discussion 0
Question # 12

According to ISO 21502, why should the organizational strategy be used?

Options:

A.  

To maximize the likelihood of success within the project environment and eliminate threats

B.  

To identify, document, and evaluate opportunities, threats, weaknesses, and strengths, which can help inform future action

C.  

To enable organizations to create tangible value instead of intangible value

Discussion 0
Question # 13

Scenario:

Exhibix is a video game developer headquartered in Zagreb, Croatia, which is known for producing therapeutic video games for children dealing with ADH

D.  

In order to improve users’ experience, Exhibix suggested undertaking a project that would enable users to interact with the virtual content in the form of holograms through augmented reality glasses in the video games. For this project, the management decided to follow the guidelines of ISO 21502 on project management.

Prior to formalizing project management, the management of Exhibix assessed, among others, the potential impacts that the project management approach may have on both internal and external stakeholders. In addition, they determined if there were sufficient resources, both human and financial, for the formalized project management. Furthermore, during this period, the management decided to assess only the nature of previous projects, due to their successful delivery.

After formalizing project management, the project board organized a meeting during which they delegated their responsibilities to the project sponsor. Following this meeting, the project sponsor and project manager proceeded to define the project phases and their time frames. Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project.

The preparations began in June, and the project manager and the team, consisting of 20 highly skilled professionals, had approximately six months to implement the project. During the implementation of the project, the project team noticed that the low maturity level of the company’s project management and the limited availability of resources were likely to have a negative impact on the performance of the project. With the deadline approaching, the team was also under a lot of pressure to close the project on time.

They were confronted with numerous challenges with the AR software, which led to the extension of the deadline for the project completion. During this period, the project office assisted the project manager and the team by providing administrative support and managing information regarding the project. Following these events, the project manager and the team were able to complete the project within the new set deadline. After the project sponsor confirmed the project closure, the AR glasses were released for use.

Question:

Based on the fourth paragraph of scenario 2, what factors did the project team notice that were likely to have a detrimental impact on the project’s performance?

Options:

A.  

Internal

B.  

External

C.  

Both A and B

Discussion 0
Question # 14

Which of the following statements describes a project termination by extinction?

Options:

A.  

The project is closed due to its failure or successful completion

B.  

The project is closed with the intention to resume at another time in the future

C.  

The project is closed due to the integration of project outputs to the operations of the parent organization

Discussion 0
Question # 15

An organization has recently initiated a project within a program. When defining the project organization structure, the head of the organization decided that the project sponsor would report to and seek direction from the program manager, who would act as the sponsoring organization with a higher-level authority. Is this acceptable?

Options:

A.  

Yes, for projects within a program, the representative of the sponsoring organization can be the program manager

B.  

No, since the program manager should report to the project sponsor

C.  

No, the project sponsor should always report to the top management, who represents the sponsoring organization that acts as a higher-level authority

Discussion 0
Question # 16

Scenario:

Tricko is a clothing manufacturer headquartered in Milano, Italy. The company was founded in 2010 by Mario, a famous Italian fashion designer. Over the last few years, the company has seen immense growth and now has a chain of stores across multiple European cities. Following industry trends, the top management of Tricko concluded that the company should establish an online store. As such, they required Lily, an experienced IT engineer, to develop a brief for this potential project. After several meetings and discussions, the top management approved the project brief and assigned Lily as the project manager. For this project, she was instructed to use the guidelines of ISO 21502 on project management.

Lily initiated the project by mobilizing the project team, which included four web developers, two network engineers, and one systems analyst. In order to ensure that every team member is fully aware of their roles and responsibilities, Lily developed team performance domains which would link each project activity with the individuals responsible for undertaking it. She explained to the team members that it is important to clearly understand their roles and responsibilities, considering that the team composition cannot be reassessed or revised once the project plan is authorized to be executed. In addition, Lily defined in a document the project’s contribution to the overall objectives of Tricko, which reflected the relevant project requirements and their associated acceptance criteria.

Following that, Lily worked with the project team to discuss project costs. She suggested the team initially establish cost estimates only for the first phase of the project and then for the entire project. In addition, she required cost estimates to be expressed in currency valuations and in labor hours. One of the network engineers suggested that each team member should provide an estimate, and then the team should reach an agreement for a joint estimate. On the other hand, one of the developers suggested establishing an estimate for the costs after the closure of the project, such as advertising and promotion costs. Lily agreed with their suggestions and asked them to provide a total estimate as soon as possible.

Based on the total estimate provided by the project team, Lily developed the project budget and created a list of project activities, divided them into smaller items, and assigned a budget for each item.

Question:

According to scenario 5, Lily defined the project budget by creating a list of project activities, dividing them into smaller items, and assigning a budget for each item. Which method did Lily use to define the project budget?

Options:

A.  

Budget by activity

B.  

Budget by baseline

C.  

Budget by line item

Discussion 0
Question # 17

Scenario:

Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture’s suppliers of wood.

Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.

Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.

A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.

Question:

Tom asked the project team to perform tasks in the predetermined order, regardless of resource shortages. What rule did Tom follow in this case?

Options:

A.  

Reflecting only sequence constraints between work packages

B.  

Reflecting sequence and resource constraints between work packages

C.  

Defining task relationships between work packages

Discussion 0
Question # 18

How does ISO 21502 define project management?

Options:

A.  

Planned and systematic actions necessary to provide confidence to the sponsoring organization and project sponsor that a project is likely to achieve its objectives

B.  

Coordinated activities to direct and control the accomplishment of agreed objectives

C.  

Principles, policies, and procedures by which a project is authorized and directed to accomplish agreed objectives

Discussion 0
Question # 19

Scenario:

Exhibix is a video game developer headquartered in Zagreb, Croatia, which is known for producing therapeutic video games for children dealing with ADH

D.  

In order to improve users’ experience, Exhibix suggested undertaking a project that would enable users to interact with the virtual content in the form of holograms through augmented reality glasses in the video games. For this project, the management decided to follow the guidelines of ISO 21502 on project management.

Prior to formalizing project management, the management of Exhibix assessed, among others, the potential impacts that the project management approach may have on both internal and external stakeholders. In addition, they determined if there were sufficient resources, both human and financial, for the formalized project management. Furthermore, during this period, the management decided to assess only the nature of previous projects, due to their successful delivery.

After formalizing project management, the project board organized a meeting during which they delegated their responsibilities to the project sponsor. Following this meeting, the project sponsor and project manager proceeded to define the project phases and their time frames. Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project.

The preparations began in June, and the project manager and the team, consisting of 20 highly skilled professionals, had approximately six months to implement the project. During the implementation of the project, the project team noticed that the low maturity level of the company’s project management and the limited availability of resources were likely to have a negative impact on the performance of the project. With the deadline approaching, the team was also under a lot of pressure to close the project on time.

They were confronted with numerous challenges with the AR software, which led to the extension of the deadline for the project completion. During this period, the project office assisted the project manager and the team by providing administrative support and managing information regarding the project. Following these events, the project manager and the team were able to complete the project within the new set deadline. After the project sponsor confirmed the project closure, the AR glasses were released for use.

Question:

Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project. Is this acceptable?

Options:

A.  

No, project phases should not overlap with one another

B.  

Yes, because it is possible that project phases can overlap

C.  

No, only the project sponsor has the authority to make a decision regarding project phases

Discussion 0
Question # 20

According to ISO 21502, how should the project benefits be maintained?

Options:

A.  

By taking corrective, and when required, preventive actions in case of deviations from the planned benefits

B.  

By collecting performance measurements for each benefit

C.  

By reporting and communicating the status of expected benefits

Discussion 0
Get ISO-21502-Lead-Project-Manager dumps and pass your exam in 24 hours!

Free Exams Sample Questions