Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: merry71

Free PRINCE2 Project Management Practitioner (Version 7) Practice Questions

Exams4sure Dumps

Exam style questions across every PRINCE2-7-Practitioner domain

Last Update 1 week ago
Total Questions : 56

Start with our free PRINCE2-7-Practitioner practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real PRINCE2 Certification exam. Each PRINCE2-7-Practitioner exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PRINCE2 weak domains, see where you're losing marks, and build a focused study plan in minutes.

PRINCE2-7-Practitioner PDF

PRINCE2-7-Practitioner PDF (Printable)
$46.5
$154.99

PRINCE2-7-Practitioner Testing Engine

PRINCE2-7-Practitioner PDF (Printable)
$51
$169.99

PRINCE2-7-Practitioner PDF + Testing Engine

PRINCE2-7-Practitioner PDF (Printable)
$63.9
$212.99
Question # 11

While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.

Is this an appropriate application of the organization practice, and why?

Options:

A.  

Yes, because the Mayor may delegate responsibility for appointing the project executive to any senior stakeholder involved in the project

B.  

Yes, because the Portfolio Director, as the business layer representative, takes responsibility for appointing the project executive

C.  

No, because it is the Mayor, as the senior elected authority, who should personally select and appoint the project executive for a project of this civic significance

D.  

No, because the responsibility for commissioning and initiating projects within the LOB portfolio rests with the Head of Portfolio Office, not the Portfolio Director

Discussion 0
Question # 12

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.  

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.  

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.  

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.  

No, because anticipated parking income means that no alternative should be assessed

Discussion 0
Question # 13

ORGANIZATION

Use the ‘Additional Information’ in the Scenario Booklet to answer this question.

Here are three roles relating to the LouisShopping Project.

Which individual (A–E) would be MOST appropriate for each role according to the ‘organization’ practice?

Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.

Options:

A.  

Regeneration Manager

B.  

Regeneration Officer

C.  

Chief Technology Officer

D.  

Heritage Manager

E.  

Portfolio Director

Roles:

Project support

User assurance

Senior supplier

Discussion 0
Question # 14

At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.

During which ‘controlling a stage’ activity should this instruction be given?

Options:

A.  

Authorize a work package

B.  

Evaluate work package status

C.  

Capture issues and risks

D.  

Take corrective action

Discussion 0
Question # 15

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.  

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.  

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.  

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.  

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Discussion 0
Question # 16

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

Options:

A.  

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.  

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.  

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.  

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages

Discussion 0

Free Exams Sample Questions