Free PRINCE2 Project Management Practitioner (Version 7) Practice Questions

Exams4sure Dumps

Exam style questions across every PRINCE2-7-Practitioner domain

Last Update 1 week ago
Total Questions : 56

Start with our free PRINCE2-7-Practitioner practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real PRINCE2 Certification exam. Each PRINCE2-7-Practitioner exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PRINCE2 weak domains, see where you're losing marks, and build a focused study plan in minutes.

PRINCE2-7-Practitioner PDF

PRINCE2-7-Practitioner PDF (Printable)
$46.5
$154.99

PRINCE2-7-Practitioner Testing Engine

PRINCE2-7-Practitioner PDF (Printable)
$51
$169.99

PRINCE2-7-Practitioner PDF + Testing Engine

PRINCE2-7-Practitioner PDF (Printable)
$63.9
$212.99
Question # 1

During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.

Which practice is being applied through the ‘controlling a stage’ process?

Options:

A.  

Business case

B.  

Organization

C.  

Plans

D.  

Quality

Discussion 0
Question # 2

Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.

Is this an appropriate application of ‘prepare the next stage plan’, and why?

Options:

A.  

Yes, because the next stage plan should reflect authorized changes, with affected product information and the project initiation documentation updated where necessary

B.  

Yes, because every authorized change must be implemented through an exception plan before the related work may enter the following stage

C.  

No, because authorized changes should remain outside the next stage plan until the project has been re-authorized by the business layer

D.  

No, because project assurance should prepare the next stage plan and update the affected product information independently of the project manager

Discussion 0
Question # 3

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

Options:

A.  

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.  

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.  

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.  

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

Discussion 0
Question # 4

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

Options:

A.  

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.  

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.  

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.  

No, because it is an exception which should be escalated in an exception report

Discussion 0
Question # 5

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

Options:

A.  

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.  

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.  

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.  

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

Discussion 0
Question # 6

PROGRESS

Here are three actions related to the ‘progress’ practice for the LouisShopping project.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.  

Project executive

B.  

Project manager

C.  

Project assurance

D.  

Team manager

E.  

Project support

Action 1:

Assist the project manager in compiling the lessons report, including the recommendation that future projects allow more time for testing and inspections.

Action 2:

When delays to the floor installation cause the stage to be forecast beyond tolerance, submit an exception report to the project board for a decision.

Action 3:

Review the exception plan and decid

Discussion 0
Question # 7

Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.

Is this an appropriate application of the issues practice, and why?

Options:

A.  

Yes, because a mature organizational approach should always be used without alteration

B.  

Yes, because portfolio funding gives the portfolio office authority to prohibit all project-level tailoring

C.  

No, because the project manager should consider the nature of the products, delivery method and project context when preparing the issue management approach

D.  

No, because product version control must be decided outside the issue management approach by the delivery teams alone

Discussion 0
Question # 8

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.  

Project executive

B.  

Senior user

C.  

Senior supplier

D.  

Project assurance

E.  

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Discussion 0
Question # 9

QUALITY

Here are three items of information relating to the testing of the solar panels during stage 4.

Under which heading of the quality register (A–E) should each item be recorded?

Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.

Options:

A.  

Quality method

B.  

Dates

C.  

Responsibilities

D.  

Result

E.  

Records

Item 1:

Specialist equipment will be used to verify that the energy output from the solar panels meets the applicable industry standards.

Item 2:

The solar-panel testing will be completed in week 2 of stage 4, one week after the security-system testing.

Item 3:

Testing found that one solar panel did not meet the required energy-output standard.

Discussion 0
Question # 10

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

Options:

A.  

Business case

B.  

Benefits management approach

C.  

Sustainability management approach

D.  

End stage report

E.  

Project brief

F.  

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will

Discussion 0

Free Exams Sample Questions