Prince2-Practitioner Dumps - PRINCE2 7 Practitioner (7th Edition) Exam Practice Exam Questions

PRINCE2 Prince2-Practitioner - PRINCE2 7 Practitioner (7th Edition) Exam Braindumps

PRINCE2 Prince2-Practitioner - PRINCE2 Certification Practice Exam

  • Certification Provider:PRINCE2
  • Exam Code:Prince2-Practitioner
  • Exam Name:PRINCE2 7 Practitioner (7th Edition) Exam
  • Certification Name:PRINCE2 Certification
  • Total Questions:263 Questions and Answers With Detailed Explanations
  • Updated on:Based on the current Prince2-Practitioner exam blueprint. Updated on Feb 18, 2026
  • Product Format: PDF (Portable) & Test Engine (Interactive) .
  • Support: 24/7 Live Chat & Email Support
  • Valid For: Worldwide - Valid In All Countries
  • Discount: Available for Bulk Purchases and Extra Licenses
  • Payment Options: PayPal, Credit/Debit Card
  • Delivery: PDF/Test Engine are Instantly Available for Download
  • Guarantee: 100% Exam Passing Assurance with Money back Guarantee.
  • Updates: 90 Days of Free Content Updates.
  •    Web Based Demo

PRINCE2 Prince2-Practitioner This Week Results

Prince2-Practitioner Question and Answers

Question # 1

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

    20% discount for all repeat customers - not cost-effective and very short term

    A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year

    A series of television and press advertisements was too expensive

    A direct mail shot to all customers - benefit would be short term

    Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Business options heading?

Options:

A.  

Produce a promotional calendar as a free Christmas gift to current and prospective customers.

B.  

Use a professional photographer to create the photographs for the calendar.

C.  

Create the photographs for the calendar internally.

D.  

Outsource the creation of the calendar to a professional marketing company.

E.  

Do nothing.

Discussion 0
Question # 2

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run

trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Expected benefits heading?

Options:

A.  

The 10-year outsourcing contract, at current prices, will be worth £80m.

B.  

Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.

C.  

The total expected savings over 10 years, at current prices, is £20m.

D.  

The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.

E.  

The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

Discussion 0
Question # 3

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

    20% discount for all repeat customers - not cost-effective and very short term

    A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year

    A series of television and press advertisements was too expensive

    A direct mail shot to all customers - benefit would be short term

    Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Costs heading?

Options:

A.  

The MNO marketing budget this year is £120k.

B.  

The project will be funded from the business marketing budget

C.  

10 further orders with an average profit of £2k will deliver a benefit of £20k in the first year.

D.  

The new company logo is estimated to cost £4k.

E.  

Project costs are estimated to be a total of £26.5k.

Discussion 0

PDF vs Software Version

Why choose Exams4sure Prince2-Practitioner Practice Test?

Stop the stress of unpredictable exam. Our Prince2-Practitioner practice test is engineered to simulate the exact format, pacing, and pressure of the real PRINCE2 Certification exam. Go beyond simple PRINCE2 7 Practitioner (7th Edition) Exam exam questions and answers; practice with Prince2-Practitioner exam dumps in an interface that mirrors the actual PRINCE2 test, building the muscle memory and confidence you need to pass on your first try.

Why Our PRINCE2 Certification Exam Dumps Are Your Ultimate Preparation Tool:

Real Exam Simulation:
Our Prince2-Practitioner practice exam interface is designed to look, feel, and function just like the real Pearson VUE testing software. From the timer countdown to the way you navigate between PRINCE2 7 Practitioner (7th Edition) Exam exam questions, there will be no surprises on exam day.

Performance Analytics:
Get more than just a score. Receive a detailed breakdown of your performance by topic area. Identify your PRINCE2 Certification certification weak spots and focus your study efforts efficiently.

Verified & Updated Questions:
Our team of PRINCE2 experts continuously updates the question bank to ensure all content is relevant, accurate, and aligned with the latest Prince2-Practitioner exam objectives.

Interactive Learning:
Read the explanation for every answer right or wrong. Understand the why behind each concept to solidify your PRINCE2 7 Practitioner (7th Edition) Exam knowledge, not just memorize a answer.

Build Exam Stamina:
Taking our full-length, timed Prince2-Practitioner practice test builds the mental endurance required to maintain focus and performance throughout the entire PRINCE2 Certification exam.

Prince2-Practitioner FAQs

You can assess product usage via Exams4sure to ensure documentation consistency.

Prince2-Practitioner Related Exams

PRINCE2 Certification Practice Exams Dumps Question Answers

  • List of Exams
  • buy now

Our Satisfied Customers

United Kingdom United Kingdom
Lynne Emulex
2 weeks ago

Passing the PRINCE2-Practitioner exam can be hard. It would be best if you bought PRINCE2-Practitioner braindumps, they are the best tool for your preparation.

Add a Comment

Comment will be moderated and published within 1-2 hours

Free Exams Sample Questions