Free Certification of Capability in Business Analysis (CCBA) Practice Questions

Question # 1

The business analyst (BA) has completed the verification of a set of requirements, but a change in scope has materialized. Which technique should the BA use to obtain consensus and reach agreement among the stakeholders?

Options:

A.  

Financial analysis

B.  

Business rules analysis

C.  

Decision analysis

D.  

Risk analysis and management

Discussion 0
Question # 2

A business analyst (BA) has completed multiple workshops involving a number of stakeholders including the project manager however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?

Options:

A.  

The project manager should decide which requirement is relevant.

B.  

The BA should select which requirements are correct.

C.  

The project manager should model requirements in a review meeting.

D.  

The BA should model the elicited requirements in a review meeting.

Discussion 0
Question # 3

A new payments system was recently implemented to replace an old legacy system. The system users have lodged a complaint that the new system is slower than the old system but system performance statistics show more efficiency. How does the business analyst (BA) demonstrate to users how the new system is performing?

Options:

A.  

Collect system metrics and communicate results in an understandable format

B.  

Identify the dependencies of the system with other applications

C.  

Analyze the feasibility of including additional hardware resources to the system

D.  

Evaluate the payments process to identify areas of improvement in the system

Discussion 0
Question # 4

The Business Requirements Document (BRD) prepared by the business analyst (BA) was circulated to stakeholders for approval. Some stakeholders objected to the Use Case diagrams and could not understand them. Why would these be included in the document?

Options:

A.  

The models were included as a mistake because Use Case diagrams are technical.

B.  

The models are part of the technical documents and not part of BRD documents.

C.  

The models are used for analysis and refining requirements and design.

D.  

The models did not change the value compared to text-based requirements

Discussion 0
Question # 5

A business analyst (BA) identified that a stakeholder requirement for an online system led to a functional requirement to provide a user login screen. This is an example of which type of traceability relationship?

Options:

A.  

Validate

B.  

Satisfy

C.  

Depend

D.  

Derive

Discussion 0
Question # 6

A business analyst (BA) is validating requirements and has found that the design cannot be validated to support the requirements. Which of the following is creating this situation?

Options:

A.  

Incorrect assumptions.

B.  

Lack of requirements traceability.

C.  

Missing requirements.

D.  

Substandard solution design.

Discussion 0
Question # 7

Verification of requirements on the projects have highlighted an issue regarding misunderstanding of design models among key stakeholders. A major reason cited for the misunderstanding was the technical jargon and models used in the documentation. What must the business analyst (BA) do to improve the understanding?

Options:

A.  

Ensure completeness within the models used

B.  

Verify that elements within the models are used consistently

C.  

Represent design models using common terminology

D.  

Check for compliance with organization standards

Discussion 0
Question # 8

A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications, which are not being updated. What is the first thing that a business analyst (BA) should consider?

Options:

A.  

Developing process and data models

B.  

Performing an interface analysis

C.  

Conducting a vendor assessment

D.  

Identifying constraints and dependencies

Discussion 0
Question # 9

A software company wants to make a gradual change from its traditional way of developing requirements to a more adaptive approach. A business analyst (BA) is hired to quantify the probability that the solution will meet the company’s needs and assess the relevant risks. Which element of risk assessment does the BA need to consider?

Options:

A.  

Issue management

B.  

Negative impact to value

C.  

Risk tolerance

D.  

Positive evaluation results

Discussion 0
Question # 10

An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the businessanalysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?

Options:

A.  

Brainstorming

B.  

Surveys

C.  

Business cases

D.  

Root cause analysis

Discussion 0
Question # 11

A business analyst (BA) is supporting an organization in its product launch. The BA wants to identify assumptions about the benefits resulting from the new product. What does identifying assumptions help the BA manage?

Options:

A.  

Metrics

B.  

Requirements

C.  

Priorities

D.  

Risks

Discussion 0
Question # 12

A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?

Options:

A.  

Item tracking methods

B.  

Requirements analysis

C.  

Requirements documentation

D.  

Metrics and KPIs

Discussion 0
Question # 13

A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?

Options:

A.  

Risk-optimizing

B.  

Risk-neutral

C.  

Risk-averse

D.  

Risk-seeking

Discussion 0
Question # 14

A business analyst (BA) is working on a project to revise the way a company bills its customers. At the end of the project, the BA creates the following matrix:

Options:

A.  

Stakeholder analysis

B.  

Root cause analysis

C.  

Business capability analysis

D.  

Strategy analysis

Discussion 0
Question # 15

A senior business analyst (BA) must review the requirements specification of a junior B

A.  

The senior BA puts together a list of key evaluation criteria to guide the determination of a requirement’s quality. Which of the criteria below is a characteristic of a quality requirement?

Options:

A.  

Mapped

B.  

Allocated

C.  

Atomic

D.  

Owned

Discussion 0

CCBA PDF

CCBA PDF (Printable)
$46.5
$154.99

CCBA Testing Engine

CCBA PDF (Printable)
$51
$169.99

CCBA PDF + Testing Engine

CCBA PDF (Printable)
$63.9
$212.99
Exams4sure Dumps

Exam style questions across every CCBA domain

Last Update 2 hours ago
Total Questions : 638

Start with our free CCBA practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Certification of Capability in Business Analysis exam. Each CCBA exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your IIBA weak domains, see where you're losing marks, and build a focused study plan in minutes.

Free Exams Sample Questions