CCP Practice Questions
Certified Cost Professional (CCP) Exam
Last Update 10 hours ago
Total Questions : 189
Dive into our fully updated and stable CCP practice test platform, featuring all the latest AACE Certification exam questions added this week. Our preparation tool is more than just a AACE International study aid; it's a strategic advantage.
Our free AACE Certification practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CCP. Use this test to pinpoint which areas you need to focus your study on.
When a person hears the words being said to him/her, but does not receive the message of the words, it is called
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?
When measuring progress using tasks that lack readily definable intermediate milestones and level of effort required is difficult to measure, the best methods to use is:

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?
An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.
The villa could be recommended for purchase at all of the below-mentioned prices except:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
The value of the truck at the end of year five (5) would be:

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?
