Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: merry71

Free Certified Cost Professional (CCP) Exam Practice Questions

Question # 51

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following is NOT an advantage of the critical path method:

Options:

A.  

The ability to determine cost overruns of critical path activities

B.  

The ability to identify activities that cannot have their schedules slip if the desired project end date is to be achieved

C.  

Reveals activities that additional resources need to be dedicated toward

D.  

The ability to show slippage in the progress of key activities

Discussion 0
Question # 52

_____________is defined as the budget for the cost (work) account times the percent complete for that account.

Options:

A.  

Percent complete

B.  

Forecast

C.  

Cost to complete

D.  

Earned value

Discussion 0
Question # 53

Question # 53

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.  

45%

B.  

50%

C.  

95%

D.  

30%

Discussion 0
Question # 54

A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

Options:

A.  

Surety bond

B.  

Performance bond

C.  

Bid bond

D.  

Liability bond

Discussion 0
Question # 55

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If there is an additional variable cost of $0.02 per unit, the monthly break even units are:

Options:

A.  

40,000 units

B.  

48,500 units

C.  

75,000 units

D.  

60,000 units

Discussion 0
Question # 56

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following statements is correct?

Options:

A.  

The graph of a normal curve is bell-shaped and is symmetrical about the standard deviation.

B.  

The graph of a normal curve is bell-shaped and is symmetrical about the variance.

C.  

Some graphic methods for describing quantitative data ate histograms and frequency distribution.

D.  

Some graphic methods for describing qualitative data are histograms and frequency distribution.

Discussion 0

CCP PDF

CCP PDF (Printable)
$45
$150

CCP Testing Engine

CCP PDF (Printable)
$60
$200

CCP PDF + Testing Engine

CCP PDF (Printable)
$89.7
$299

Free Exams Sample Questions