Exclusive Black Friday Deal: 70% Off All Exam Bundles! Use coupon code below to unlock your savings! - Ends in 0d 00h 00m 00s - Coupon code: Friday70

Free CompTIA Project+ Certification (2026) Practice Questions

Question # 111

A project manager is developing a project management plan. The resource assignments are complete. Which of the following steps should have been completed before completing the resource assignments?

Options:

A.  

Determine the budget considerations.

B.  

Develop a kickoff presentation.

C.  

Review the existing artifacts.

D.  

Define the units of work.

Discussion 0
Question # 112

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

Options:

A.  

Dashboard

B.  

Gantt chart

C.  

Work breakdown structure

D.  

Requirements Traceability Matrix

Discussion 0
Question # 113

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

Options:

A.  

Approving deliverables

B.  

Enforcing vendor rules of engagement

C.  

Reporting overall process

D.  

Scheduling team touch points

Discussion 0
Question # 114

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

Options:

A.  

Obtain details from the owner of the project.

B.  

Update the critical path for the project.

C.  

Apply contingency reserves.

D.  

Reestimate epic user stories.

Discussion 0
Question # 115

Which of the following concepts represents multiple resources interfaced to run reports?

Options:

A.  

Code repository

B.  

Data warehouse

C.  

Storage server

D.  

File-sharing system

Discussion 0
Question # 116

Which of the following would a scrum team discuss during a daily stand-up meeting?

Options:

A.  

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.  

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.  

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.  

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Discussion 0
Question # 117

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.  

Kanban board

B.  

Pareto chart

C.  

Ishikawa diagram

D.  

Decision tree

Discussion 0
Question # 118

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.  

Digital security

B.  

Physical security

C.  

Data security

D.  

Operational security

Discussion 0
Question # 119

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.  

Pareto chart

B.  

Milestone chart

C.  

Burndown chart

D.  

Gantt chart

Discussion 0
Question # 120

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

Options:

A.  

Build

B.  

Subscription

C.  

Lease

D.  

Buy

Discussion 0

PK0-005 PDF

PK0-005 PDF (Printable)
$46.5
$154.99

PK0-005 Testing Engine

PK0-005 PDF (Printable)
$51
$169.99

PK0-005 PDF + Testing Engine

PK0-005 PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions