Question # 41

Which of the following is the best example of CapEx?

Options:

A.  

Taxes

B.  

Vehicles

C.  

Salaries

D.  

Utilities

Discussion 0
Question # 42

Which of the following items must be protected as Pll? (Select TWO).

Options:

A.  

Job title

B.  

Home address

C.  

Work phone number

D.  

Time zone

E.  

Date of birth

F.  

Blood type

Discussion 0
Question # 43

Which of the following describes three-tier architecture?

Options:

A.  

Conceptual, design, and implementation stages

B.  

Presentation, application, and data processing

C.  

Network, software, and security

D.  

Development, testing, and production environment

Discussion 0
Question # 44

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Question # 44

Which of the following most likely represents the number of items in the backlog?

Options:

A.  

23

B.  

5

C.  

10

D.  

15

Discussion 0
Question # 45

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.  

Rational Unified Process

B.  

Waterfall

C.  

Agile

D.  

DevOps

Discussion 0
Question # 46

Which of the following is a quality assurance tool?

Options:

A.  

Defining project goals

B.  

Identifying the root cause analysis

C.  

Assessing employee efficiency

D.  

Assessing skill gaps

Discussion 0
Question # 47

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

Options:

A.  

Request a change control ticket.

B.  

Review the schedule plan.

C.  

Refine the project documentation.

D.  

Revise the communication plan.

Discussion 0
Question # 48

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

Options:

A.  

Milestone chart

B.  

Gantt chart

C.  

PERT chart

D.  

WBS

Discussion 0
Question # 49

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.  

Escalate directly to the project sponsor

B.  

Push the kickoff meeting out by one week

C.  

Proceed with the kickoff as planned

D.  

Identity replacements for project stakeholders

Discussion 0
Question # 50

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.  

Update the WBS.

B.  

Escalate to the CC

B.  

C.  

Accept the change.

D.  

Implement the change.

Discussion 0

PK0-005 PDF

PK0-005 PDF (Printable)
$46.5
$154.99

PK0-005 Testing Engine

PK0-005 PDF (Printable)
$51
$169.99

PK0-005 PDF + Testing Engine

PK0-005 PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions