Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free CompTIA Project+ Certification (2026) Practice Questions

Exams4sure Dumps

Exam style questions across every PK0-005 domain

Last Update 2 days ago
Total Questions : 460

Start with our free PK0-005 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Project+ exam. Each PK0-005 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your CompTIA weak domains, see where you're losing marks, and build a focused study plan in minutes.

PK0-005 PDF

PK0-005 PDF (Printable)
$54.25
$154.99

PK0-005 Testing Engine

PK0-005 PDF (Printable)
$59.5
$169.99

PK0-005 PDF + Testing Engine

PK0-005 PDF (Printable)
$74.55
$212.99
Question # 31

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

Options:

A.  

IaaS

B.  

XaaS

C.  

DaaS

D.  

SaaS

Discussion 0
Question # 32

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

Options:

A.  

Establish communication channels

B.  

Plan a kickoff meeting

C.  

Develop a responsibility assignment matrix

D.  

Identify the stakeholders

Discussion 0
Question # 33

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.  

Identify project risks and plans to address them.

B.  

Identify business needs and product descriptions.

C.  

Create a work breakdown structure for the project.

D.  

Create a work schedule for the project team to follow.

Discussion 0
Question # 34

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.  

Information disposal

B.  

Information classification

C.  

Information access administration

D.  

Information backup

Discussion 0
Question # 35

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

Options:

A.  

Gantt chart

B.  

Milestone chart

C.  

Velocity chart

D.  

PERT chart

Discussion 0
Question # 36

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

Options:

A.  

Call the previous PM for advice on risks and issues.

B.  

Ask the project sponsor to provide previous final project report results.

C.  

Complete the project charter using the other PM ' s subject matter expertise.

D.  

Use existing artifacts and accommodate based on the current project success criteria.

Discussion 0
Question # 37

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.  

Assess the documentation.

B.  

Obtain stakeholder feedback.

C.  

Review the project objectives.

D.  

Mitigate risks.

Discussion 0
Question # 38

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

Options:

A.  

Each feature will have a different owner.

B.  

The majority of the team can only meet on a weekly basis.

C.  

The stakeholders have provided a specific deadline to meet.

D.  

Each feature has a specific budget allocation.

Discussion 0
Question # 39

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:

A.  

Notify customers the downtime will take longer than expected.

B.  

Add new team members to help speed up validation.

C.  

Begin executing the rollback plan.

D.  

Record the issue and proceed with the implementation.

Discussion 0
Question # 40

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.  

Hold a new backlog prioritization meeting.

B.  

Add milestones to check the project ' s progress.

C.  

Adjust the task relationship to complete coding in advance.

D.  

Apply contingency buffers to the critical path.

Discussion 0

Free Exams Sample Questions