Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free CompTIA Project+ Certification (2026) Practice Questions

Exams4sure Dumps

Exam style questions across every PK0-005 domain

Last Update 2 days ago
Total Questions : 460

Start with our free PK0-005 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Project+ exam. Each PK0-005 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your CompTIA weak domains, see where you're losing marks, and build a focused study plan in minutes.

PK0-005 PDF

PK0-005 PDF (Printable)
$54.25
$154.99

PK0-005 Testing Engine

PK0-005 PDF (Printable)
$59.5
$169.99

PK0-005 PDF + Testing Engine

PK0-005 PDF (Printable)
$74.55
$212.99
Question # 21

A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?

Options:

A.  

Share

B.  

Exploit

C.  

Mitigate

D.  

Avoid

Discussion 0
Question # 22

Which of the following contract types in project procurement has the highest risk for the buyer?

Options:

A.  

Time and material

B.  

Cost-plus

C.  

Fixed-price

D.  

Unit price

Discussion 0
Question # 23

Which of the following roles helps a team achieve its sprint objective?

Options:

A.  

Product owner

B.  

Scrum master

C.  

Project manager

D.  

Business analyst

Discussion 0
Question # 24

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Options:

A.  

Work breakdown structure

B.  

Change log

C.  

Project success criteria

D.  

Milestone chart

Discussion 0
Question # 25

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.  

Regression testing

B.  

Smoke testing

C.  

Stress testing

D.  

Automation testing

Discussion 0
Question # 26

Which of the following best describes a rollback plan?

Options:

A.  

Apply an alternative plan if the original plan does not work.

B.  

Return to the operational state of a system before applying a requested change.

C.  

Restart the project with new resources to avoid failures from previous ones.

D.  

Repeat the tasks suggested in the requested change until they work.

Discussion 0
Question # 27

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Options:

A.  

Time to be fixed

B.  

Impact to project

C.  

Issue category

D.  

Resource availability

Discussion 0
Question # 28

An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?

Options:

A.  

Consult other developers.

B.  

Escalate the issue to the project steering committee.

C.  

Request the developer provide justification.

D.  

Decline the invoice.

Discussion 0
Question # 29

A customer requests some changes to a product, and those changes are approved by the CC

B.  

Which of the following should be changed first?

Options:

A.  

ROI

B.  

KPI

C.  

RACI

D.  

SOW

Discussion 0
Question # 30

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

Options:

A.  

Awareness of the local environment

B.  

Awareness of the brand value

C.  

Awareness of the resource constraints

D.  

Awareness of the company ' s mission

Discussion 0

Free Exams Sample Questions