Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-001 Project Management Professional v5 is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-001 Practice Questions

Project Management Professional v5

Last Update 4 days ago
Total Questions : 918

Dive into our fully updated and stable PMI-001 practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-001. Use this test to pinpoint which areas you need to focus your study on.

PMI-001 PDF

PMI-001 PDF (Printable)
$43.75
$124.99

PMI-001 Testing Engine

PMI-001 PDF (Printable)
$50.75
$144.99

PMI-001 PDF + Testing Engine

PMI-001 PDF (Printable)
$63.7
$181.99
Question # 111

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

Options:

A.  

US$158,700

B.  

US$172,500

C.  

US$187,500

D.  

US$245,600

Discussion 0
Question # 112

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.  

Estimate Costs

B.  

Control Costs

C.  

Plan Cost Management

D.  

Determine Budget

Discussion 0
Question # 113

The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan is known as:

Options:

A.  

Initiating.

B.  

Planning.

C.  

Executing.

D.  

Monitoring and Controlling.

Discussion 0
Question # 114

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.  

Acquire Project Team.

B.  

Plan Human Resource Management.

C.  

Manage Project Team.

D.  

Develop Project Team.

Discussion 0
Question # 115

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Options:

A.  

$800

B.  

$1000

C.  

$1250

D.  

$1800

Discussion 0
Question # 116

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Options:

A.  

1.33

B.  

2

C.  

0.75

D.  

0.5

Discussion 0
Question # 117

Variance and trend analysis is a tool and technique used in which process?

Options:

A.  

Perform Qualitative Risk Analysis

B.  

Perform Quantitative Risk Analysis

C.  

Control Risks

D.  

Plan Risk Responses

Discussion 0
Question # 118

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

Options:

A.  

Risk response planning

B.  

Manage stakeholders

C.  

Scope definition

D.  

Performance reporting

Discussion 0
Question # 119

Project Management Process Groups are linked by:

Options:

A.  

the outputs they produce

B.  

discrete or one-time events

C.  

the project management plan

D.  

common tools and techniques

Discussion 0
Question # 120

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.  

Executing

B.  

Planning

C.  

Monitoring and Controlling

D.  

Initiating

Discussion 0