Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-100 Certified Associate in Project Management (CAPM)® is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-100 Practice Questions

Certified Associate in Project Management (CAPM)®

Last Update 3 days ago
Total Questions : 704

Dive into our fully updated and stable PMI-100 practice test platform, featuring all the latest CAPM exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free CAPM practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-100. Use this test to pinpoint which areas you need to focus your study on.

PMI-100 PDF

PMI-100 PDF (Printable)
$43.75
$124.99

PMI-100 Testing Engine

PMI-100 PDF (Printable)
$50.75
$144.99

PMI-100 PDF + Testing Engine

PMI-100 PDF (Printable)
$63.7
$181.99
Question # 31

An input to the Manage Project Team process is:

Options:

A.  

Work performance reports.

B.  

Change requests.

C.  

Activity resource requirements.

D.  

Enterprise environmental factors.

Discussion 0
Question # 32

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.  

Project management plan.

B.  

Project charter.

C.  

Work breakdown structure.

D.  

Stakeholder register.

Discussion 0
Question # 33

A tool or technique used in the Control Procurements process is:

Options:

A.  

Expert judgment.

B.  

Performance reporting.

C.  

Bidder conferences.

D.  

Reserve analysis.

Discussion 0
Question # 34

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.  

Facilitation techniques

B.  

Expert judgment

C.  

Analytical techniques

D.  

Variance analysis

Discussion 0
Question # 35

When should quality planning be performed?

Options:

A.  

While developing the project charter

B.  

In parallel with the other planning processes

C.  

As part of a detailed risk analysis

D.  

As a separate step from the other planning processes

Discussion 0
Question # 36

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Options:

A.  

Close Project or Phase

B.  

Conduct Procurements

C.  

Control Procurements

D.  

Close Procurements

Discussion 0
Question # 37

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.  

Cost Plus Incentive Fee (CPIF)

B.  

Fixed Price Incentive Fee (FPIF)

C.  

Cost Pius Award Re (CPAF)

D.  

Time and Material (T&M)

Discussion 0
Question # 38

An output of the Develop Project Team process is:

Options:

A.  

Organizational process assets.

B.  

Enterprise environmental factors updates.

C.  

Project staff assignments.

D.  

Organizational charts and position descriptions.

Discussion 0
Question # 39

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.  

Urgent information need

B.  

Sensitivity of information

C.  

Project environment

D.  

Ease of use

Discussion 0
Question # 40

An output of the Create WBS process is:

Options:

A.  

Scope baseline.

B.  

Change requests.

C.  

Accepted deliverables.

D.  

Variance analysis.

Discussion 0