Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Associate in Project Management (CAPM)® Practice Questions

Exams4sure Dumps

Exam style questions across every PMI-100 domain

Last Update 3 days ago
Total Questions : 704

Start with our free PMI-100 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each PMI-100 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

PMI-100 PDF

PMI-100 PDF (Printable)
$54.25
$154.99

PMI-100 Testing Engine

PMI-100 PDF (Printable)
$59.5
$169.99

PMI-100 PDF + Testing Engine

PMI-100 PDF (Printable)
$74.55
$212.99
Question # 81

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.  

Estimate Costs

B.  

Estimate Activity Resources

C.  

Control Costs

D.  

Determine Budget

Discussion 0
Question # 82

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.  

Monitoring and Controlling

B.  

Initiating

C.  

Planning

D.  

Executing

Discussion 0
Question # 83

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.  

Bottom-up

B.  

Parametric

C.  

Analogous

D.  

Three-point

Discussion 0
Question # 84

Cost baseline is an output of which of the following processes?

Options:

A.  

Control Costs

B.  

Determine Budget

C.  

Estimate Costs

D.  

Estimate Activity Resources

Discussion 0
Question # 85

The following chart contains information about the tasks in a project.

Question # 85

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.  

0.83

B.  

0.9

C.  

1.11

D.  

1.33

Discussion 0
Question # 86

Requirements documentation will typically contain at least:

Options:

A.  

Stakeholder requirements, staffing requirements, and transition requirements.

B.  

Business requirements, the stakeholder register, and functional requirements.

C.  

Stakeholder impact, budget requirements, and communications requirements.

D.  

Business objectives, stakeholder impact, and functional requirements.

Discussion 0
Question # 87

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.  

outlines team selection guidelines and team member responsibilities.

B.  

establishes project roles and responsibilities.

C.  

improves teamwork, interpersonal skills, and competencies.

D.  

provides an accurate appraisal of team member performance.

Discussion 0
Question # 88

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Options:

A.  

work package

B.  

deliverable

C.  

milestone

D.  

activity

Discussion 0
Question # 89

A tool and technique used in the Develop Project Charter process is:

Options:

A.  

change control tools

B.  

expert judgment

C.  

meetings

D.  

analytical techniques

Discussion 0
Question # 90

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.  

Business case

B.  

Work breakdown structure

C.  

Requirements documentation

D.  

Risk register

Discussion 0

Free Exams Sample Questions