Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-SP PMI Scheduling Professional is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-SP Practice Questions

PMI Scheduling Professional

Last Update 3 days ago
Total Questions : 323

Dive into our fully updated and stable PMI-SP practice test platform, featuring all the latest PMI Certification exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Certification practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-SP. Use this test to pinpoint which areas you need to focus your study on.

PMI-SP PDF

PMI-SP PDF (Printable)
$43.75
$124.99

PMI-SP Testing Engine

PMI-SP PDF (Printable)
$50.75
$144.99

PMI-SP PDF + Testing Engine

PMI-SP PDF (Printable)
$63.7
$181.99
Question # 41

Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project team are planning in detail all of the things the team will need to create, purchase, or do in order to satisfy the project scope. Management is concerned with the activity which Frank is using in this scenario, as they believe that Frank is taking too long to complete this pre-execution activity. Which of the following techniques of the activity process is Frank using in this example?

Options:

A.  

Rolling wave planning

B.  

Expert judgment

C.  

Creating a project template

D.  

Decomposition

Discussion 0
Question # 42

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Options:

A.  

Risk management plan

B.  

Schedule management plan

C.  

Risk register

D.  

Activity attributes

Discussion 0
Question # 43

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.  

Project change control process

B.  

Perform integrated change control process

C.  

Configuration management

D.  

Communications management

Discussion 0
Question # 44

You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

Options:

A.  

Project is behind the schedule.

B.  

Costs are higher than planned.

C.  

Project is right on target.

D.  

Project is ahead of the schedule.

Discussion 0
Question # 45

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options:

A.  

Decomposition

B.  

Rolling wave plan

C.  

Precedence diagramming method

D.  

Templates

Discussion 0
Question # 46

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

Options:

A.  

Communications management plan

B.  

Issues log

C.  

Project schedule

D.  

Schedule management plan

Discussion 0
Question # 47

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

Options:

A.  

Contract Types

B.  

Expert Judgment

C.  

Procurement Negotiations

D.  

Make-or-Buy Analysis

Discussion 0
Question # 48

Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

Options:

A.  

Critical chain method

B.  

Risk analysis method

C.  

Activity on the arrow method

D.  

Critical path method

Discussion 0