Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Contract Manager Practice Questions

Exams4sure Dumps

Exam style questions across every CCM domain

Last Update 1 day ago
Total Questions : 140

Start with our free CCM practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Contract Manager exam. Each CCM exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your FIDIC weak domains, see where you're losing marks, and build a focused study plan in minutes.

CCM PDF

CCM PDF (Printable)
$54.25
$154.99

CCM Testing Engine

CCM PDF (Printable)
$59.5
$169.99

CCM PDF + Testing Engine

CCM PDF (Printable)
$74.55
$212.99
Question # 41

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

Options:

A.  

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.  

The Contractor cannot terminate the Contract.

C.  

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.  

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

Discussion 0
Question # 42

(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)

Options:

A.  

Contractor

B.  

Engineer

C.  

Employer

Discussion 0

Free Exams Sample Questions