Start with our free CCM practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Contract Manager exam. Each CCM exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your FIDIC weak domains, see where you're losing marks, and build a focused study plan in minutes.
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)