Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

CCM Certified Contract Manager is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

CCM Practice Questions

Certified Contract Manager

Last Update 1 day ago
Total Questions : 140

Dive into our fully updated and stable CCM practice test platform, featuring all the latest Contract Manager exam questions added this week. Our preparation tool is more than just a FIDIC study aid; it's a strategic advantage.

Our free Contract Manager practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CCM. Use this test to pinpoint which areas you need to focus your study on.

CCM PDF

CCM PDF (Printable)
$43.75
$124.99

CCM Testing Engine

CCM PDF (Printable)
$50.75
$144.99

CCM PDF + Testing Engine

CCM PDF (Printable)
$63.7
$181.99
Question # 1

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

Options:

A.  

When the works are simple and of short duration.

B.  

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.

C.  

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.

D.  

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.

Discussion 0
Question # 2

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:

A.  

True

B.  

False

Discussion 0
Question # 3

Which one statement is correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.  

Instructions to Tenderers are part of the Employer ' s Requirements.

B.  

No Data other than required by the General Conditions of Contract may be entered in the Contract Data.

C.  

Instructions to Tenderers may require the tenderer to provide information on matters in Sub-Clause 4.3 on Contractor ' s Representative and Sub-Clause 6.12 on Key Personnel.

D.  

General Conditions of Contract cannot be amended as it may imbalance the obligations and rights of the Parties.

Discussion 0
Question # 4

In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)

Options:

A.  

The Engineer

B.  

The Engineer ' s Resident Engineer

C.  

The Employer

D.  

The Employer ' s Representative

Discussion 0
Question # 5

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.  

True

B.  

False

Discussion 0
Question # 6

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

Options:

A.  

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

B.  

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

C.  

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor ' s items on the Site.

D.  

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor ' s items on the Site if the Contractor fails, as this is the Contractor ' s obligation.

Discussion 0
Question # 7

(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)

Options:

A.  

True

B.  

False

Discussion 0
Question # 8

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

Options:

A.  

Both you and Y are both correct.

B.  

You are correct, Y is wrong.

C.  

You are wrong, Y is correct.

D.  

Both you and Y are wrong.

Discussion 0
Question # 9

The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?

Choose all of the correct answers (multiple possibilities):

Options:

A.  

The advance payment is to help the Contractor to finance some of its early cost and expenditure until it becomes entitled to first (non-interim) payment.

B.  

The advance payment reflects the amount of works the Contractor has already performed up to the moment such advance payment is performed.

C.  

Under the General Conditions, the amount of advance payment is to be paid in full by the Employer through one instalment.

D.  

Under the General Conditions, the advance payment will be repaid by deducting all amounts from invoices until the entire advance payment is repaid.

Discussion 0
Question # 10

(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))

Options:

A.  

Yes, but Contractor will do so on its own risk.

B.  

Yes, Contractor can start design and execution of the Works to make sure it won ' t lose any time.

C.  

No, because any design or execution before the Commencement Date is prohibited in Clause 8.

D.  

Yes, but Contractor will do so on Employer ' s risk.

Discussion 0
Get CCM dumps and pass your exam in 24 hours!

Free Exams Sample Questions