Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: merry71

Free Construction Documents Technologist Practice Questions

Exams4sure Dumps

Exam style questions across every CDT domain

Last Update 13 hours ago
Total Questions : 120

Start with our free CDT practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CDT Certification exam. Each CDT exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your Construction Specifications Institute weak domains, see where you're losing marks, and build a focused study plan in minutes.

CDT PDF

CDT PDF (Printable)
$46.5
$154.99

CDT Testing Engine

CDT PDF (Printable)
$51
$169.99

CDT PDF + Testing Engine

CDT PDF (Printable)
$63.9
$212.99
Question # 21

Which of the following elements should be included in Supplementary Conditions?

Options:

A.  

Requirements for a schedule of values

B.  

Claims and dispute resolution requirements

C.  

Equal employment opportunity requirements

D.  

Termination of the work by owner or contractor

Discussion 0
Question # 22

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.  

A collaborative, integrated, and productive team composed of key project participants

B.  

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.  

Responsibility silos for greater efficiencies, leading to project success

D.  

Segregat knowledge gathered as needed with paper-based communications to team members

Discussion 0
Question # 23

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

Options:

A.  

Workflow meeting

B.  

Preinstallation meeting

C.  

Progress meeting

D.  

Schedule monitoring meeting

Discussion 0
Question # 24

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?

Options:

A.  

Methods technique

B.  

Critical path method

C.  

Front end loading

D.  

Schedule of values

Discussion 0
Question # 25

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.  

Traditional drawing set organization

B.  

Uniform Drawing System

C.  

AIA CAD Layer Guidelines

D.  

BIM Implementation

Discussion 0
Question # 26

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.  

Building code

B.  

Quality control standard

C.  

Reference standard

D.  

Specification master

Discussion 0
Question # 27

Procedural requirements for alternates, project meetings, and submittals belong where?

Options:

A.  

Divisions 02-49

B.  

The general conditions

C.  

The supplementary conditions

D.  

Division 01

Discussion 0
Question # 28

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:

A.  

The construction schedule

B.  

The subcontractor’s invoices

C.  

The schedule of values

D.  

The percentage of completion

Discussion 0
Question # 29

In construction documents, what does the agreement refer to?

Options:

A.  

The agreement between the owner and the architect/engineer

B.  

The general conditions of the contract for construction

C.  

The agreement between the owner and the contractor

D.  

The agreement between the contractor and the subcontractor

Discussion 0
Question # 30

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

Options:

A.  

Conformed set

B.  

Record set

C.  

Change order log

D.  

Request for information documents

Discussion 0

Free Exams Sample Questions