Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

P1 Management Accounting is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

P1 Practice Questions

Management Accounting

Last Update 3 days ago
Total Questions : 260

Dive into our fully updated and stable P1 practice test platform, featuring all the latest CIMA Operational exam questions added this week. Our preparation tool is more than just a CIMA study aid; it's a strategic advantage.

Our free CIMA Operational practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about P1. Use this test to pinpoint which areas you need to focus your study on.

P1 PDF

P1 PDF (Printable)
$122.5
$350

P1 Testing Engine

P1 PDF (Printable)
$130.9
$374

P1 PDF + Testing Engine

P1 PDF (Printable)
Question # 11

RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day.  110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed.  60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT’s existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.

Select ALL the true statements.

Options:

A.  

The cost for the production director meeting was a relevant cost.

B.  

Material A was a relevant cost.

C.  

Material B was a relevant cost.

D.  

The components are to be purchased from HY at a cost of $50 each. This is a relevant cost because it is future expenditure that will be incurred as a result of the work being undertaken.

E.  

The machine is currently being leased and it has spare capacity so it will either stand idle or be used on this work. The lease cost will be a relevant cost or $10 per hour.

F.  

The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour. This is a relevant cost.

G.  

The relevant cost is $7010

Discussion 0
Question # 12

A company is choosing between three projects, Project P, Project Q and Project R using minimax regret as the criterion for the decision. The outcome from each project is dependent on future economic growth. If this is strong, returns will be P $5,000, Q $6,500 and R $7,200. If it is weak, returns will be P $3,500, Q $4,800 and R $4,200.

Place the correct figures into the table to show the maximum regret for each project.

Question # 12

Options:

Discussion 0
Question # 13

An analysis of past sales data shows that the underlying trend in a company's sales volume can be represented by:

Y = 50X + 625

Where Y is the trend sales units for a quarter and X is the quarterly period number.

The seasonal variation index values have been identified as follows:

Question # 13

The forecast sales volume in units for quarter 4 next year, which is period 14, is:

Options:

A.  

1,378

B.  

1,325

C.  

1,329

D.  

1,274

Discussion 0
Question # 14

A company’s management is considering investing in a project with an expected life of 4 years. It has a positive net present value of $180,000 when cash flows are discounted at 8% per annum. The project’s cash flows include a cash outflow of $100,000 for each of the four years. No tax is payable on projects of this type.

The percentage increase in the annual cash outflow that would cause the company’s management to reject the project from a financial perspective is, to the nearest 0.1%:

Options:

A.  

54.3%

B.  

45.0%

C.  

55,6%

D.  

184.0%

Discussion 0
Question # 15

Which of the following statements about total quality management are incorrect? Select ALL that apply.

Options:

A.  

The culture of an organisation should be to get things right the first time.

B.  

Everyone within an organisation should be involved in improving quality.

C.  

All costs relating to quality should be examined, particularly those relating to failure costs.

D.  

There is an acceptable quality level that an organisation must try to achieve.

E.  

The costs of conformance are more important than the costs of non-conformance.

F.  

The organisation should rely on inspection to achieve quality standards.

Discussion 0
Question # 16

A medium-sized manufacturing company, which operates in the electronics industry, has employed a firm of consultants to carry out a review of the company’s planning and control systems. The company presently uses a traditional incremental budgeting system and the inventory management system is based on economic order quantities (EOQ) and reorder levels. The company’s normal production patterns have changed significantly over the previous few years as a result of increasing demand for customized products. This has resulted in shorter production runs and difficulties with production and resource planning. The consultants have recommended the implementation of activity based budgeting and a manufacturing resource planning system to improve planning and resource management.

What are the benefits for the company that could occur following the introduction of an activity based budgeting system?

Select ALL the correct answers.

Options:

A.  

Under an activity based budgeting system, resource allocation is linked to the strategic plan and is prepared after considering alternative strategies. This approach ensures that new activities that are required to meet the company’s strategic objectives are included in the budget.

B.  

Under a traditional incremental budgeting system the focus is on existing resources and operations. Adjustments are then made for changes in activity and price which results in past inefficiencies being perpetuated. Under an activity based budgeting system, only resources that are needed to perform activities required to meet the budgeted production and sales volumes are included.

C.  

Activity based techniques including activity based budgeting focus on the outputs of a process rather than the input to the process. This approach provides a clear framework for understanding the link between costs and the level of activity. It allows the ranking of activities and the determination of how limited resources should be allocated across competing activities.

D.  

Activity Based Budgeting Systems present costs under functional headings i.e. the emphasis is on the nature of the cost. The weakness if this approach is that it gives little indication of the link between the level of activity and the cost incurred.

E.  

The approach under an Activity based Budgeting System is to make arbitrary cuts in order to meet overall financial targets.

Discussion 0
Question # 17

MDS is facing a temporary shortage of Material H which is used to produce all three of its products.

In order to maximise its profitability, which product should be manufactured first?

Options:

A.  

The product using the least amount of Material H per unit.

B.  

The product with the highest contribution per kg of Material H.

C.  

The product with the highest contribution per unit.

D.  

The product with the highest profit per unit.

Discussion 0
Question # 18

Changing to a just-in-time, from a traditional, manufacturing environment can affect cost accounting systems.

Which of the following statements is correct?

Options:

A.  

Larger volumes of inventory must be recorded

B.  

A greater number of individual supplier records must be maintained

C.  

More frequent, smaller deliveries from suppliers must be recorded

D.  

Less frequent, larger deliveries from suppliers must be recorded

Discussion 0
Question # 19

A master budget comprises the...

Options:

A.  

budgeted income statement and budgeted cash flow statement only.

B.  

budgeted income statement and budgeted balance sheet only.

C.  

budgeted income statement and budgeted capital expenditure only

D.  

budgeted income statement, budgeted balance sheet and budgeted cash flow statement only.

Discussion 0
Question # 20

Which of the following explain why standard costing is less appropriate in the contemporary business environment?

1. In a continuous improvement environment standard costing can restrict the impetus to remain as cost competitive as rivals.

2. Fixed overhead variances are less relevant as fixed costs represent a decreasing proportion of total manufacturing cost.

3. In a just-in-time environment there are fewer costs to control.

Options:

A.  

1 only

B.  

1 and 2

C.  

2 and 3

D.  

1 and 3

Discussion 0
Get P1 dumps and pass your exam in 24 hours!

Free Exams Sample Questions