Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-PBA PMI Professional in Business Analysis is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-PBA Practice Questions

PMI Professional in Business Analysis

Last Update 3 days ago
Total Questions : 200

Dive into our fully updated and stable PMI-PBA practice test platform, featuring all the latest PMI Professional in Business Analysis exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Professional in Business Analysis practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-PBA. Use this test to pinpoint which areas you need to focus your study on.

PMI-PBA PDF

PMI-PBA PDF (Printable)
$69.65
$199

PMI-PBA Testing Engine

PMI-PBA PDF (Printable)
$78.75
$225

PMI-PBA PDF + Testing Engine

PMI-PBA PDF (Printable)
$87.15
$249
Question # 31

Question # 31

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

Options:

A.  

1

B.  

2

C.  

3

D.  

4

Discussion 0
Question # 32

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.  

Compare reported defects with user acceptance test results.

B.  

Escalate the issue to the project manager since the acceptance was given by the customer.

C.  

Do nothing since the solution is now the responsibility of the operations manager.

D.  

Involve the end users and plan a new round of acceptance tests to check the gaps.

Discussion 0
Question # 33

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

Options:

A.  

The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.

B.  

The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

C.  

The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

D.  

The business analyst should have invited the key stakeholders to the meeting.

Discussion 0
Question # 34

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

Options:

A.  

User stories

B.  

Functional specifications

C.  

Flow chart

D.  

Prototyping

Discussion 0
Question # 35

Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?

Options:

A.  

Stakeholder satisfaction survey

B.  

Interface analysis

C.  

Process modeling

D.  

Sectiead Traceability matrix

Discussion 0
Question # 36

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

Options:

A.  

Bring the subsequent project to the change control board (CCB).

B.  

Ask the stakeholders to review the requirement before any other action is taken.

C.  

Communicate that the status of this requirement has changed.

D.  

Mark the requirement as complete so that it is not forgotten.

Discussion 0
Question # 37

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Options:

A.  

Time-boxing

B.  

SWOT analysis

C.  

Weighted ranking

D.  

Multivoting

Discussion 0
Question # 38

A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.

Which key factor drives the selection of business analyst activities to be included in the project?

Options:

A.  

Communication plan

B.  

Project life cycle

C.  

Return on investment (ROI)

D.  

Payback period

Discussion 0
Question # 39

A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.

Which technique will allow the business analyst to determine this information?

Options:

A.  

Payback period

B.  

Net present value (NPV)

C.  

Internal rate of return

D.  

Return on investment (ROI)

Discussion 0
Question # 40

Question # 40

Which solution should be chosen according to the completed weighted-ranking matrix?

Options:

A.  

Outsource the development.

B.  

Purchase off-the-shelf software.

C.  

Develop in-house software.

D.  

Enhance the existing system.

Discussion 0
Get PMI-PBA dumps and pass your exam in 24 hours!

Free Exams Sample Questions