AgilePM-Practitioner Practice Questions
Agile Project Management (AgilePM) Practitioner Exam
Last Update 1 day ago
Total Questions : 184
Dive into our fully updated and stable AgilePM-Practitioner practice test platform, featuring all the latest AgilePM exam questions added this week. Our preparation tool is more than just a APMG-International study aid; it's a strategic advantage.
Our free AgilePM practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about AgilePM-Practitioner. Use this test to pinpoint which areas you need to focus your study on.
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in
the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?
What action should the Project Manager take to plan the deployment activities?
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully
meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture
Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall ' s
specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,
until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
Maintainability is a required attribute of the initial delivered solution
Deliver first, re-engineer later
Short-term, tactical solution

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
How should the Project Manager encourage the contractors to turn up on time?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development

Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?


