The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .
Is this an appropriate suggestion?)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.
What should the Developers do to help Hira make this decision?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which of the following actions is NOT appropriate when using when using MoSCoW prioritization to manage business expectations related to the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
(At a meeting, Hira reminded all project participants of their role responsibilities.
Which statement does NOT comply with AgilePM?)
(In the Ecolodge Panthera Resort (EPR) Project, answer the following questions about risk management.
In addition to the Developers, the teams include:
Mira Bachar (Guest Services Manager) – Product Owner for both Delivery Teams
Lee Tan (General Manager) – Business Advisor
Brinda Vyas – Business Visionary
Hira – Project Manager
Sukra Aroon – Solutions Architect
Wanida Anong – Regulatory Compliance Manager
Sarah Lark – Business Sponsor
Priya – Business Advisor
Select 2 answers to each question.
Which 2 statements describe the application of AgilePM ' s approach to managing risk?)
Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
· Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the
issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(During the Sprint, Mira Bachar identified inconsistencies between what she wanted, expressed in Product Backlog items, and the Product Increments delivered by the Delivery Teams.
Which 2 of the following would be appropriate actions for Mira to take in the next Sprint?)
(During the Foundations phase, Brinda Vyas organized a workshop that Hira facilitated. It was attended by Sukra Aroon, Mira, Lee Tan, and Developers from the two Delivery Teams. The goal was to define and align on what would be available for guests at the end of Project Increment 4.
Considering the workshop attendees, which of the following observations aligns with AgilePM?)