Certified Tester Advanced Level Test Management (CTAL-TM) v3.0

Last Update 3 months ago
Total Questions : 228

Dive into our fully updated and stable CTAL-TM practice test platform, featuring all the latest Test Manager Advanced exam questions added this week. Our preparation tool is more than just a ISTQB study aid; it's a strategic advantage.

Our free Test Manager Advanced practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CTAL-TM. Use this test to pinpoint which areas you need to focus your study on.

CTAL-TM PDF

CTAL-TM PDF (Printable)
$43.75
$124.99

CTAL-TM Testing Engine

CTAL-TM PDF (Printable)
$50.75
$144.99

CTAL-TM PDF + Testing Engine

CTAL-TM PDF (Printable)
$63.7
$181.99
Question # 21

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

Options:

A.  

Function points

B.  

Extrapolation

C.  

Planning poker

D.  

Three-point estimation

Discussion 0
Question # 22

It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?

Options:

A.  

Forming Professional

B.  

Storming Social

C.  

Norming Personal

D.  

Performing Methodological

Discussion 0
Question # 23

You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the pipeline to augment their unit tests so they will have continuous testing. They have already determined that this is technically possible with the tool you are using but with require some changes to the test automation framework to integrate the results reporting

What will your team need to make this happen?

Options:

A.  

Investigation that the tool will be fit for purpose

B.  

Training regarding how to make the framework modifications so the integration is possible

C.  

A review to determine if this is the best tool to use for the integration with the CI/CD pipeline

D.  

investigation of the licensing models of the tool and an understanding of any potential costs

Discussion 0
Question # 24

You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?

Options:

A.  

Social

B.  

Professional

C.  

Methodological

D.  

Biological

Discussion 0
Question # 25

Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team is worried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team

Which competences will be most important for your ambassadors to possess?

Options:

A.  

Professional competence and methodological competence

B.  

Methodological competence and social competence

C.  

Social competence and personal competence

D.  

Personal competence and professional competence

Discussion 0
Question # 26

You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

Options:

A.  

Wideband defphi

B.  

Planning poker

C.  

Three-point estimation

D.  

Extrapolation

Discussion 0
Question # 27

Which of the following best describes the appraisal costs in the cost of quality'

Options:

A.  

The cost spent preventing defects from occurring in the first place

B.  

The cost for performing dynamic testing

C.  

The cost for fixing defects

D.  

The cost for lawyers to deal with a lawsuit over a defect

Discussion 0
Question # 28

You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''

Options:

A.  

Sequential

B.  

Hybrid as a transition to Agile

C.  

Agile

D.  

Hybrid as fit for purpose

Discussion 0
Question # 29

If you are monitoring code coverage during testing to determine what areas still need testing what type of testing is likely occurring?

Options:

A.  

Black-box

B.  

White-box

C.  

Functional

D.  

Non-functional

Discussion 0
Question # 30

You are working on a project that is having problems with regressions. With each release of software given to the test team. 50% of the defects found are actually regressions. To combat this you have decided to implement test automation. You have given your automation team the following goal

'Implement lest automation to automate 90% of the manual regression tests before the product release date.’’

Which of the following is likely an issue with this goal being defined as "SMART?

Options:

A.  

it is not clear if this is achievable in the time allowed

B.  

It is not specific on what needs to be done

C.  

It is not relevant to the project objectives

D.  

It is not measurable against the goals of the project

Discussion 0