Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

ISEB-PM1 BCS Foundation Certificate in IS Project Management is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

ISEB-PM1 Practice Questions

BCS Foundation Certificate in IS Project Management

Last Update 22 hours ago
Total Questions : 625

Dive into our fully updated and stable ISEB-PM1 practice test platform, featuring all the latest Project & programme management and consultancy certifications exam questions added this week. Our preparation tool is more than just a BCS study aid; it's a strategic advantage.

Our free Project & programme management and consultancy certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about ISEB-PM1. Use this test to pinpoint which areas you need to focus your study on.

ISEB-PM1 PDF

ISEB-PM1 PDF (Printable)
$43.75
$124.99

ISEB-PM1 Testing Engine

ISEB-PM1 PDF (Printable)
$50.75
$144.99

ISEB-PM1 PDF + Testing Engine

ISEB-PM1 PDF (Printable)
$63.7
$181.99
Question # 11

Risk event is the description of what may happen to the _____ of the project.

Options:

A.  

Budget

B.  

harm

C.  

Schedule

D.  

Manager

Discussion 0
Question # 12

Stakeholder analysis identifies what information and relates it to the purpose of the project?

Options:

A.  

Requirements, influence, and functional department

B.  

Interest, requirements, and functional role

C.  

Requirements, expectations, and influence

D.  

Interest, expectations, and influence

Discussion 0
Question # 13

What should a project manager do with low-priority risks?

Options:

A.  

Ignore low-priority risks

B.  

Monitor periodically with other low-priority risks

C.  

Create a mitigation plan for the low-priority risks

D.  

Increase the contingency reserve

Discussion 0
Question # 14

The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk.

This new risk is which of the following types of risk?

Options:

A.  

Secondary

B.  

Primary

C.  

Residual

D.  

Tertiary

Discussion 0
Question # 15

You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:

Options:

A.  

See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis

B.  

Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation

C.  

Look for someone to blame before you see the sponsor

D.  

Do nothing until the slippage occurs

E.  

Immediately inform the sponsor and ask for advice

Discussion 0
Question # 16

Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement.

Which of the following is not contained in the project scope statement?

Options:

A.  

Requested changes

B.  

Project configuration management requirements

C.  

Constraints

D.  

Project specifications

Discussion 0
Question # 17

A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response.

Which of the following is the BEST thing for the project manager to do?

Options:

A.  

Document the new risks and continue the Plan Risk Responses process.

B.  

Make sure the project work is better understood.

C.  

Spend more time making sure the risk responses are clearly defined.

D.  

Get more people involved in the Identify Risks process since risks have been missed.

Discussion 0
Question # 18

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

Options:

A.  

Risk response planning

B.  

Manage stakeholders

C.  

Scope definition

D.  

Performance reporting

Discussion 0
Question # 19

When would resource leveling be applied to a schedule model?

Options:

A.  

Before constraints have been identified

B.  

Before it has been analyzed by the critical path method

C.  

After it has been analyzed by the critical path method

D.  

After critical activities have been removed from the critical path

Discussion 0
Question # 20

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.  

Applying calendars

B.  

Resource Leveling

C.  

Resource Planning

D.  

Resource Conflict Management

Discussion 0