Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

ISEB-PM1 BCS Foundation Certificate in IS Project Management is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

ISEB-PM1 Practice Questions

BCS Foundation Certificate in IS Project Management

Last Update 23 hours ago
Total Questions : 625

Dive into our fully updated and stable ISEB-PM1 practice test platform, featuring all the latest Project & programme management and consultancy certifications exam questions added this week. Our preparation tool is more than just a BCS study aid; it's a strategic advantage.

Our free Project & programme management and consultancy certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about ISEB-PM1. Use this test to pinpoint which areas you need to focus your study on.

ISEB-PM1 PDF

ISEB-PM1 PDF (Printable)
$43.75
$124.99

ISEB-PM1 Testing Engine

ISEB-PM1 PDF (Printable)
$50.75
$144.99

ISEB-PM1 PDF + Testing Engine

ISEB-PM1 PDF (Printable)
$63.7
$181.99
Question # 31

What does a CPI value greater than 1.0 indicate?

Options:

A.  

Cost right at the estimated value

B.  

Cost under the estimated value

C.  

Cost right at the actual value

D.  

Cost over the estimated value

Discussion 0
Question # 32

Conflict should be best addressed in which manner?

Options:

A.  

Early, in private, using a direct, collaborative approach

B.  

Early, in public, using an indirect, collaborative approach

C.  

Early, in private, using an indirect, cooperative approach

D.  

As late as possible, in public, using a direct, confrontational approach

Discussion 0
Question # 33

What is included in a control chart?

Options:

A.  

Baseline

B.  

Planned value

C.  

Upper specification limit

D.  

Expenditure

Discussion 0
Question # 34

The decomposition technique is used to do which of the following?

Options:

A.  

Subdivide the estimated costs of individual activities

B.  

Subdivide project deliverables and project work into smaller, more manageable components

C.  

Relate the work packages to the performing organizational units

D.  

Shorten the project schedule duration and the amount of resources needed

Discussion 0
Question # 35

Decomposition is a tool and technique used in which of the following?

Options:

A.  

Define Scope and Define Activities

B.  

Collect Requirements and Estimate Activity Resources

C.  

Create WBS and Define Activities

D.  

Create WBS and Estimate Activity Duration

Discussion 0
Question # 36

Which of the following must not performed in the project initiation process?

Options:

A.  

Evaluate historical information

B.  

List down business need

C.  

List down stakeholders

D.  

Create scope statement

Discussion 0
Question # 37

Which describes how cost variances will be managed?

Options:

A.  

Cost management plan

B.  

Cost baseline

C.  

Cost estimate

D.  

Chart of accounts

Discussion 0
Question # 38

Which of the following correctly explains the term "progressive elaboration"?

Options:

A.  

Changing project specifications continuously

B.  

Elaborate tracking of the project progress

C.  

Elaborate tracking of the project specifications with a change control system

D.  

Project specifications becoming more explicit and detailed as the project progresses

Discussion 0
Question # 39

When is a project finished?

Options:

A.  

After verbal acceptance of the customer or sponsor

B.  

After lessons learned have been documented in contract closure

C.  

When the project objectives have been met

D.  

After resources have been released

Discussion 0
Question # 40

Which of the following is an example of a technique used in quantitative risk analysis?

Options:

A.  

Sensitivity analysis

B.  

Probability and impact matrix

C.  

Risk data quality assessment

D.  

Risk categorization

Discussion 0
Get ISEB-PM1 dumps and pass your exam in 24 hours!

Free Exams Sample Questions