Dive into our fully updated and stable LEED-Green-Associate practice test platform, featuring all the latest Leadership in Energy and Environmental Design (LEED) exam questions added this week. Our preparation tool is more than just a USGBC study aid; it's a strategic advantage.

Our free Leadership in Energy and Environmental Design (LEED) practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about LEED-Green-Associate. Use this test to pinpoint which areas you need to focus your study on.

LEED-Green-Associate PDF

LEED-Green-Associate PDF (Printable)
$43.75
$124.99

LEED-Green-Associate Testing Engine

LEED-Green-Associate PDF (Printable)
$50.75
$144.99

LEED-Green-Associate PDF + Testing Engine

LEED-Green-Associate PDF (Printable)
$63.7
$181.99
Question # 31

By which phase should you establish the energy performance targets?

Options:

A.  

Contract Administration

B.  

Construction Documents

C.  

Programming

D.  

Schematic Design

Discussion 0
Question # 32

The U.S. Green Building Council (USGBC) member logo may be displayed when

Options:

A.  

the organization is a member of USGBC

B.  

a professional is a member of the local USGBC chapter

C.  

a professional successfully passes the LEED AP exam

D.  

the project team successfully completes and certifies a project with the LEED Rating System

Discussion 0
Question # 33

What is considered as the receptacle load?

Options:

A.  

The electrical current drawn by regulated and non-regulated receptacles

B.  

The electrical current drawn by the individual receptacle connected to a standby battery

C.  

The electrical current Which is non-regulated and has major impact on the load 0t the overall network

D.  

The electrical current drawn by all equipment that is connected to the electrical system via a wall outlet

Discussion 0
Question # 34

Which statement is the U.S. Green Building Council vision?

Options:

A.  

A transformed built environment leading to a sustainable future

B.  

Buildings and communities will regenerate and sustain the health and vitality of all life within a generation

C.  

Meeting the goals of the Paris Agreement and improving the lives of millions of citizens through better buildings

D.  

To transform the building and construction sector across three strategic areas - climate action, health and wellbeing and resources and circularity

Discussion 0
Question # 35

Solar Reflectance Index (SRI) combines reflectivity with:

Options:

A.  

Transmissivity

B.  

Emissivity

C.  

Absorptivity

D.  

Conductivity

Discussion 0
Question # 36

During the pre-design phase of a three-story office building, the project team determines that the anticipated energy use of the proposed building will exceed the Owner's Project Requirements (OPR). What strategy should the project team consider in order to lower the building's energy use?

Options:

A.  

Increase the square footage of the building

B.  

Maximize daylighting opportunities with properly sized and oriented windows

C.  

Use valid survey protocols to assess occupants' satisfaction with the indoor environment

D.  

Monitor and verity performance to ensure that building systems are functioning as designed

Discussion 0
Question # 37

The LEED reviewer advised a project team that an inappropriate rating system was chosen for a newly constructed school in operation for one year and undergoing minor improvements. What should the project team have done differently to avoid this error?

Options:

A.  

Allow the LEED Project Administrator sole responsibility to review the appropriate rating system for the project

B.  

Select LEED for Schools New Construction and Major Renovations Rating System, as this project is classified as a school

C.  

Select LEED for Existing Buildings: Operations and Maintenance Rating System, as the Operational and Maintenance phase has begun

D.  

Review the appropriate rating system and determine the best adaptation to use with consultation from U.S. Green Building Council

Discussion 0
Question # 38

When determining total parking capacity available to building users, which of the following must be included?

Options:

A.  

Motorbike and bicycle parking spaces

B.  

Parking spaces for fleet vehicles used for business

C.  

On-street parking spaces on public rights of way

D.  

New and existing surface parking spaces

Discussion 0
Question # 39

Which of the following is a strategy for preventing light pollution?

Options:

A.  

Install up-lighting

B.  

Install shielded fixtures

C.  

Install high performance windows

D.  

Use dark paving materials to diminish light distribution

Discussion 0
Question # 40

What rating system should a project use if 55% of the project's gross floor area is appropriate to certify under LEED BD+C and 45% is appropriate under LEED O+M?

Options:

A.  

Project team must decide which rating system is most applicable

B.  

LEED Green Associate must decide

C.  

LEED BD+C

D.  

LEED O+M