Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free LEED Green Associate GAFRE Exam (LEED GA) Practice Questions

Exams4sure Dumps

Exam style questions across every LEED-Green-Associate domain

Last Update 3 days ago
Total Questions : 430

Start with our free LEED-Green-Associate practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real Leadership in Energy and Environmental Design (LEED) exam. Each LEED-Green-Associate exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your USGBC weak domains, see where you're losing marks, and build a focused study plan in minutes.

LEED-Green-Associate PDF

LEED-Green-Associate PDF (Printable)
$54.25
$154.99

LEED-Green-Associate Testing Engine

LEED-Green-Associate PDF (Printable)
$59.5
$169.99

LEED-Green-Associate PDF + Testing Engine

LEED-Green-Associate PDF (Printable)
$74.55
$212.99
Question # 51

Which of the following has the highest energy consumption in a typical U.S. office building?

Options:

A.  

Lighting

B.  

Cooling

C.  

Space Heating

D.  

Water Heating

Discussion 0
Question # 52

Which of the following factors contributes to improved general health of building occupants and construction workers?

Options:

A.  

High VOC building materials

B.  

Post-occupancy flush outs

C.  

Application of construction management practices

D.  

Low ventilation rates

Discussion 0
Question # 53

What is process water?

Options:

A.  

Blackwater used for irrigation purposes

B.  

Water used for industrial processes and building systems, such as cooling towers and chillers

C.  

Domestic waste water composed 0t wash water from kitchens and bathrooms

D.  

Spent or used water from a home, community, farm or industry that contains dissolved or suspended matter

Discussion 0
Question # 54

What is the process that is performed on existing buildings to identify and recognize system improvements that make the building more suitable for current use?

Options:

A.  

Energy modeling

B.  

Retrocommissioning

C.  

Life-cycle assessment

D.  

Fundamental Commissioning (Cx)

Discussion 0
Question # 55

The intent of waste management in the Materials and Resources credit category is to

Options:

A.  

specify the use of green materials

B.  

promote the use of rapidly renewable resources

C.  

reduce the amount of waste and toxins hauled to landfills

D.  

increase the use of pre-consumer/post-consumer recycled content

Discussion 0
Question # 56

Which of the following Is a strategy for improving Indoor Environmental Quality during construction?

Options:

A.  

Cover duct work with plastic

B.  

Store absorptive-finish materials directly on slab

C.  

Collect construction debris in the mechanical room

D.  

Run permanently installed HVAC with final filtration media

Discussion 0
Question # 57

At which stage should the coordination of building and site systems be addressed to maximize the impact of integrative process?

Options:

A.  

Predesign

B.  

Detailed Design

C.  

Post Occupancy

D.  

Schematic Design

Discussion 0
Question # 58

The LEED credits given the greatest weights are credits that

Options:

A.  

are used in certifying a LEED Platinum Project

B.  

contribute to developmental density and Sustainable Sites

C.  

are included in the LEED for Buildings Operations and Maintenance: Existing Buildings rating system

D.  

most directly address the most important environmental impacts and human benefits

Discussion 0
Question # 59

What is the optimal method to divert solid waste from landfills?

Options:

A.  

Recover

B.  

Reduce

C.  

Reuse

D.  

Recycle

Discussion 0
Question # 60

Which of the following approaches refers to the identification and quantification of environmental effects throughout the life of the materials andproducts used in a project as well as the project itself?

Options:

A.  

Commissioning

B.  

Integrative process

C.  

Life-cycle costing (LCC)

D.  

Life-cycle assessment (LCA)

Discussion 0