Start with our free PMI-002 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each PMI-002 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the standard deviation for the estimates?
If BCWP= 450: ACWP= 410, and BCWS= 325, what is the schedule variance and the schedule performance index?
18 You are the project manager of a software company. As software development can be very chaotic, your company has decided to follow a more rigorous approach to software development. Specifically your company has chosen to adopt the extreme programming XP methodology for your current software project. The XP methodology is highly iterative, and produces numerous deliverables include UML diagrams, architecture diagrams, prototypes and test-cases. Assume you are in the Sequence Activities phase of the project. Which of the following sequencing methods should you use to identify the logical relationships between tasks, so that the activities can be sequenced correctly?
Which of the following illustrate a chart with upper or lower limits on which value of some statistical measure for a series of samples are plotted using sample measure measurement, where the mean and standard deviation are determine from the sample selected?
You are the project manager of a large construction project. The project objective is to construct a set of buildings in the city within 18 months from the project start date. Resources are not readily available because they are currently assigned to other projects. Nick, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Nick assigned to your project?
According to the PMBOK guide, the project statement of work(SOW) should contain or reference to all the following elements except ?
The Person primarily responsible for the quality of deliverables is the.