Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Exams4sure Dumps

Exam style questions across every PMI-002 domain

Last Update 3 days ago
Total Questions : 748

Start with our free PMI-002 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each PMI-002 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

PMI-002 PDF

PMI-002 PDF (Printable)
$54.25
$154.99

PMI-002 Testing Engine

PMI-002 PDF (Printable)
$59.5
$169.99

PMI-002 PDF + Testing Engine

PMI-002 PDF (Printable)
$74.55
$212.99
Question # 81

Which of the following is NOT true about Analogous Estimate Costs ?

Options:

A.  

Does not require high expertise on part of estimators as estimates are based on previous projects

B.  

Uses Expert Judgment

C.  

Useful in early phases of the project

D.  

Used when reference projects are similar

Discussion 0
Question # 82

Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?

Options:

A.  

Collect Requirements

B.  

Initiation

C.  

Control Scope

D.  

Define Scope

Discussion 0
Question # 83

Change requests are made against the ____________?

Options:

A.  

Project baseline

B.  

SOW

C.  

Charter

D.  

Executive summary

Discussion 0
Question # 84

Project risk is defined as the cumulative effect of chances of ________ which will adversely affect project objectives.

Options:

A.  

Likely events

B.  

Complex activities

C.  

Complex schedules

D.  

Uncertain occurrences

Discussion 0
Question # 85

The Staffing Management Plan ___________, will be formal or informal.

Options:

A.  

Depending on the size and complexity of the project

B.  

Depending on the management

C.  

Depending on the project manager

D.  

Depending on the size only

Discussion 0
Question # 86

A Reserve Analysis is a technique for:

Options:

A.  

Estimate Activity Durations

B.  

Estimate Activity Resources

C.  

Sequence Activities

D.  

Define Activities

Discussion 0
Question # 87

Project scope is:

Options:

A.  

The work that must be done in order to deliver a product with the specified features and functions.

B.  

The features and functions that are to be included in a product or service.

C.  

A narrative description of work to be performed under contract.

D.  

a and b

Discussion 0
Question # 88

A Project Scope Management includes :

Options:

A.  

Initiation

B.  

Project Plan Execution

C.  

Overall Change Control

D.  

Report Performance

Discussion 0
Question # 89

Which is not included in General Management :

Options:

A.  

Finance and accounting

B.  

Strategic planning

C.  

Sales and marketing

D.  

Developing a new product or service

Discussion 0
Question # 90

In which type of organization, a project manager is in complete control of the project?

Options:

A.  

Projectized organization

B.  

Balanced Matrix organization

C.  

Strong Matrix

D.  

Weak Matrix organization

Discussion 0