Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Question # 41

Group brainstorming encourages all of the following except _________.

Options:

A.  

Team building

B.  

Analysis of alternatives

C.  

Convergent thinking

D) Q Uninhibited verbalization

Discussion 0
Question # 42

Which of the following are inputs of Develop Project Charter process?

Options:

A.  

Project statement of work, Contract, Business case and organizational process assets

B.  

Project SOW, project selection methods, and enterprise environmental factors

C.  

Contract, project selection methods, enterprise environmental factors, and organizational process assets

D.  

Contract, project SOW, enterprise environmental factors, and organizational process assets

Discussion 0
Question # 43

What-if scenario analysis is done as a part of __________ process.

Options:

A.  

Sequence Activities

B.  

Develop Schedule

C.  

Control Schedule

D.  

Define Activities

Discussion 0
Question # 44

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called ____________.

Options:

A.  

Negotiation

B.  

Arbitration

C.  

Smoothing

D.  

Forcing

Discussion 0
Question # 45

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

Options:

A.  

Procurement Management

B.  

Planning Management

C.  

Scope Management

D.  

Control Management

Discussion 0
Question # 46

An approved change request is an input to which of the following processes?

Options:

A.  

Define Scope

B.  

Verify Scope

C.  

Monitor and Control Project Work

D.  

Integrated Change Control

Discussion 0
Question # 47

How much time does a typical project manager spend communicating both formally and informally?

Options:

A.  

40-60%

B.  

50-70%

C.  

60-80%

D.  

75-90%

Discussion 0
Question # 48

You are the project manager of a project. You have to determine the staffing requirements of the project. Which of the following you need:

Options:

A.  

Resource breakdown schedule

B.  

Responsibility assignment matrix

C.  

Work breakdown structure

D.  

Organization chart

Discussion 0
Question # 49

The ___________ documents the characteristics of the product or service that the project was undertaken to create.

Options:

A.  

Project charter

B.  

Scope statement

C.  

Product description

D.  

Technical article

Discussion 0
Question # 50

The core planning processes include:

Options:

A.  

Collect Requirements, Sequence Activities, and Plan Communications

B.  

Plan Quality, Plan Communications, and Risk Response Development

C.  

Define Scope, Estimate Activity Durations, and Determine Budget

D.  

Collect Requirements, Define Activities, Estimate Costs, Plan Quality, and Plan Risk Responses

Discussion 0

PMI-002 PDF

PMI-002 PDF (Printable)
$46.5
$154.99

PMI-002 Testing Engine

PMI-002 PDF (Printable)
$51
$169.99

PMI-002 PDF + Testing Engine

PMI-002 PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions