PMI-002 Practice Questions

Certified Associate in Project Management (CAPM) Certification

Last Update 3 days ago
Total Questions : 748

Dive into our fully updated and stable PMI-002 practice test platform, featuring all the latest CAPM exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free CAPM practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-002. Use this test to pinpoint which areas you need to focus your study on.

PMI-002 PDF

PMI-002 PDF (Printable)
$43.75
$124.99

PMI-002 Testing Engine

PMI-002 PDF (Printable)
$50.75
$144.99

PMI-002 PDF + Testing Engine

PMI-002 PDF (Printable)
$63.7
$181.99
Question # 11

Which of the following is conflict resolution technique?

Options:

A.  

Compromise

B.  

Smoothing

C.  

Foimal

D.  

Coercive

Discussion 0
Question # 12

How many communication channels will be required in a project in which 5 individual are participating?

Options:

A.  

10

B.  

12

C.  

4

D.  

5

Discussion 0
Question # 13

The end of the project comes after which of the following?

Options:

A.  

Project charter

B.  

F'na' deliverable

C.  

Schedule

D.  

QA activities are done

Discussion 0
Question # 14

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.

Options:

A.  

Enterprise benefits measurement methods when selecting a project

B.  

Integral parts of the SOW

C.  

Ways to ensure stakeholder commitment

D.  

Project selection methods

Discussion 0
Question # 15

Delivery dates and availability of resources can be found in the details of the __________.

Options:

A.  

Work Breakdown Structure

B.  

sow

C.  

Project Charter

D.  

Project Scope Statement

Discussion 0
Question # 16

What is a corrective action?

Options:

A.  

An action that brings future project events Into alignment with the project plan

B.  

An action to correct something in the project

C.  

An action to prevent something in the project

D.  

Corrective action is not related to project

Discussion 0
Question # 17

Which of the following activities is not part of Plan Risk Management?

Options:

A.  

Updating risk register

B.  

Determining risk roles and responsibilities

C.  

Identifying risk categories

D.  

Developing a risk management plan

Discussion 0
Question # 18

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

Options:

A.  

Schedule

B.  

Assumption

C.  

Constraint

D.  

Planning process

Discussion 0
Question # 19

Which one of the following is not an output of contract closure?

Options:

A.  

c'ose contracts

B.  

Lessons learned documentation

C.  

Deliverable acceptance

D.  

Scope statement

Discussion 0
Question # 20

If a project with a CPI of 0.8, what you tell?

Options:

A.  

The project is consuming more resources than anticipated.

B.  

The project is using fewer resources than anticipated.

C.  

The project is falling behind.

D.  

The project is running ahead of schedule.

Discussion 0