Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free PRINCE2 7 Foundation written Exam Practice Questions

Exams4sure Dumps

Exam style questions across every Prince2-Foundation domain

Last Update 3 days ago
Total Questions : 471

Start with our free Prince2-Foundation practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real P3O exam. Each Prince2-Foundation exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PRINCE2 weak domains, see where you're losing marks, and build a focused study plan in minutes.

Prince2-Foundation PDF

Prince2-Foundation PDF (Printable)
$54.25
$154.99

Prince2-Foundation Testing Engine

Prince2-Foundation PDF (Printable)
$59.5
$169.99

Prince2-Foundation PDF + Testing Engine

Prince2-Foundation PDF (Printable)
$74.55
$212.99
Question # 21

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.  

Define the period over which the cost-benefit analysis will be based

B.  

Describe how to measure the performance of the project's products in operational use

C.  

Define the scope, timing and ownership of the benefit reviews required

D.  

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Discussion 0
Question # 22

From whom does a Team Manager obtain approval for a completed product?

Options:

A.  

Project Manager

B.  

Project Support

C.  

The authority defined in the Product Description

D.  

Senior Supplier

Discussion 0
Question # 23

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

Options:

A.  

Specify the desired result

B.  

Provide the resources and skills to deliver the desired result

C.  

Pay for the project

D.  

Specify the benefits of the project

Discussion 0
Question # 24

Which is a purpose of the Closing a Project process?

Options:

A.  

Authorize the final stage of the project

B.  

Confirm that all benefits defined in the Business Case have been achieved

C.  

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.  

Delegate day-to-day management of the end of the project to the Project Manager

Discussion 0
Question # 25

Which does the Executive need to ensure is in place before the project is initiated?

Options:

A.  

All Work Packages are authorized

B.  

An understanding of how the project will contribute to corporate objectives

C.  

The Project Plan has been approved

D.  

The Project Initiation Documentation is complete

Discussion 0
Question # 26

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Options:

A.  

Project Brief

B.  

Project Initiation Documentation

C.  

Project mandate

D.  

Benefits Review Plan

Discussion 0
Question # 27

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.  

corporate, programme management or the customer

B.  

the project board

C.  

the project manager

D.  

the change authority

Discussion 0
Question # 28

Which describes a project benefit?

Options:

A.  

A specialist product of the project

B.  

The result of a change derived from using the project's products

C.  

An uncertain result caused by project actions

D.  

A measurable improvement resulting from an outcome

Discussion 0
Question # 29

Which describes a risk event?

Options:

A.  

The area of uncertainty in terms of the threat or opportunity

B.  

The derivation or sources of a potential risk to the project

C.  

The achievement of a milestone on the project plan

D.  

The sequence of events and actions that will be put in place if a risk occurs

Discussion 0
Question # 30

Which is a purpose of a Lessons Log?

Options:

A.  

Note any lessons that are raised in Checkpoint Reports

B.  

Record that corrective action is being taken

C.  

Escalate lessons to the Project Board

D.  

Raise improvements with Project Assurance

Discussion 0

Free Exams Sample Questions