Free PRINCE2 7 Foundation written Exam Practice Questions

Exams4sure Dumps

Exam style questions across every Prince2-Foundation domain

Last Update 3 days ago
Total Questions : 471

Start with our free Prince2-Foundation practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real P3O exam. Each Prince2-Foundation exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PRINCE2 weak domains, see where you're losing marks, and build a focused study plan in minutes.

Prince2-Foundation PDF

Prince2-Foundation PDF (Printable)
$54.25
$154.99

Prince2-Foundation Testing Engine

Prince2-Foundation PDF (Printable)
$59.5
$169.99

Prince2-Foundation PDF + Testing Engine

Prince2-Foundation PDF (Printable)
$74.55
$212.99
Question # 41

Which is a purpose of the quality theme?

Options:

A.  

To establish how the project will ensure that all products created meet their requirements

B.  

To establish baselines against which any changes to products can be assessed

C.  

To identify all the products of the project to ensure the scope has been adequately defined

D.  

To determine the communication needs of the organization’s quality assurance function

Discussion 0
Question # 42

What is established during the 'initiating a project' process?

Options:

A.  

The agreed protect acceptance criteria

B.  

The need for a configuration library

C.  

A plan for the work or project initiation

D.  

An understanding of the project's funding

Discussion 0
Question # 43

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.  

1 and 2

B.  

2 and 3

C.  

3 and 4

D.  

1 and 4

Discussion 0
Question # 44

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

Options:

A.  

project assurance

B.  

the project board

C.  

the corporate, programme management or the customer

D.  

a team manager

Discussion 0
Question # 45

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

Options:

A.  

Management strategies

B.  

Plan

C.  

Stakeholder interests

D.  

Time-driven controls

Discussion 0
Question # 46

Which control must be used as a minimum requirement for applying the 'progress' theme?

Options:

A.  

A project plan

B.  

Tolerances

C.  

An Issue register

D.  

Highlight reports

Discussion 0
Question # 47

Which is an objective of the Starting up a Project process?

Options:

A.  

Identify who will be responsible for creating the Project Plan

B.  

Agree how the project will be monitored and controlled after initiation

C.  

Authorize the Project Manager to proceed with the initiation stage

D.  

Agree how issues and changes will be identified, assessed and controlled

Discussion 0
Question # 48

Which is a purpose of the Risk Register?

Options:

A.  

Describe the risk management techniques and standards to be applied to the project

B.  

Act as a central record of information relating to the identified risks for the project

C.  

Act as a repository for informal issues

D.  

List the responsibilities for achieving an effective risk management procedure

Discussion 0
Question # 49

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.  

By providing a common understanding of the products required

B.  

By providing the tolerances for the project manager’s objectives

C.  

By providing roles descriptions for the project management team

D.  

By providing the justification for the project

Discussion 0
Question # 50

Which statement applies to Stage Plans?

Options:

A.  

Always have the same duration as the Project Plan

B.  

Are produced at the same time as the Project Initiation Documentation

C.  

Assist the Project Manager in the day-to-day running and control of the project

D.  

Provide a baseline against which the Project Board monitor overall progress

Discussion 0