Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PSM-I Professional Scrum Master I is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PSM-I Practice Questions

Professional Scrum Master I

Last Update 3 days ago
Total Questions : 296

Dive into our fully updated and stable PSM-I practice test platform, featuring all the latest Professional Scrum Master exam questions added this week. Our preparation tool is more than just a Scrum study aid; it's a strategic advantage.

Our free Professional Scrum Master practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PSM-I. Use this test to pinpoint which areas you need to focus your study on.

PSM-I PDF

PSM-I PDF (Printable)
$43.75
$124.99

PSM-I Testing Engine

PSM-I PDF (Printable)
$50.75
$144.99

PSM-I PDF + Testing Engine

PSM-I PDF (Printable)
$63.7
$181.99
Question # 1

(Which of the following are the Developers accountable for?

Choose the best two answers.)

Options:

A.  

Reporting productivity.

B.  

Organizing the work required to meet the Sprint Goal.

C.  

Creating a plan for the Sprint, the Sprint Backlog.

D.  

Selecting the Product Owner.

Discussion 0
Question # 2

Who has the final say on the order of the Product Backlog?

Options:

A.  

The Development Team.

B.  

The Product Owner.

C.  

The Scrum Master.

D.  

The Stakeholders.

E.  

The CEO.

Discussion 0
Question # 3

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.  

The Developers after clarifying requirements with the Product Owner

B.  

The Scrum Master.

C.  

The Product Owner with input from the Developers.

D.  

The Developers, alone.

E.  

The most senior people in the organization, including architects and subject matter experts.

Discussion 0
Question # 4

(Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

Choose the best answer.)

Options:

A.  

The Project Manager.

B.  

The Product Owner.

C.  

The Scrum Master.

D.  

The Scrum Team.

E.  

All of the above.

Discussion 0
Question # 5

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

Options:

A.  

True

B.  

False

Discussion 0
Question # 6

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

Options:

A.  

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.  

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.  

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.  

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.  

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Discussion 0
Question # 7

Every Development Team should have:

Options:

A.  

At least one representative from each major software engineering discipline (like QA, Dev, UX).

B.  

The competencies and skills needed to deliver a Done Increment in a Sprint.

C.  

One Lead Developer and no more than 8 other members.

Discussion 0
Question # 8

A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what “Done” means. (Choose two.)

Options:

A.  

All work the Development Team is willing to do.

B.  

Ready for integration.

C.  

No work left from the definition of “Done”.

D.  

Whatever the Product Owner defines as quality.

E.  

All work to create software that is ready to be released to end users.

Discussion 0
Question # 9

When do Development Team members take ownership of a Sprint Backlog item?

Options:

A.  

At the Sprint planning meeting.

B.  

During the Daily Scrum.

C.  

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.  

Whenever a team member can accommodate more work.

Discussion 0
Question # 10

A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?

Options:

A.  

Add security to the definition of “Done”.

B.  

Tell the Product Owner to stop further development of features until the issues are fixed.

C.  

Create a Product Backlog item for security.

D.  

Go check with the testers.

E.  

Ask the person to share the issue with the team as soon as possible.

Discussion 0
Get PSM-I dumps and pass your exam in 24 hours!

Free Exams Sample Questions