Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Planning & Scheduling Professional (PSP) Exam Practice Questions

Question # 21

What are Phases based on and derived from?

Options:

A.  

Resources

B.  

Constructability

C.  

Score of Work

D.  

Budget

Discussion 0
Question # 22

At the end of month one, did the delay to the parking structure foundation delay the project?

Options:

A.  

NO.

B.  

Yes, by 4 calendar days.

C.  

Yes, by 14 calendar days.

D.  

Yes, by 9 calendar days.

Discussion 0
Question # 23

What problems can a soils engineer deal with on a project?

Options:

A.  

Survey error.

B.  

Hidden subsurface conditions.

C.  

Archeological findings.

D.  

Toxic soils.

Discussion 0
Question # 24

Determine the correct formula and date for the late finish for Activity 2001.

Question # 24

Options:

A.  

L

F.  

2001 - 1 day -> 08-28-01.

B.  

LS.2002- 1 day-> 08-29-01.

C.  

LS.2002 + 1 day -> 08-30-01.

D.  

LS.2002 - 1 day -> 08-28-01.

Discussion 0
Question # 25

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.  

$289.000

B.  

$321.000

C.  

$193,000

D.  

$327,000

Discussion 0
Question # 26

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Options:

A.  

Is a milestone.

B.  

It is on the critical path.

C.  

Was completed in the past.

D.  

Has yet to be completed.

Discussion 0
Question # 27

When are KPIs defined?

Options:

A.  

At project initiation

B.  

At NTP

C.  

At the start of the Construction Phase

D.  

After the Bidding Phase

Discussion 0
Question # 28

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

Question # 28

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Question # 28

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.  

$420,000.

B.  

$307,000.

C.  

$524,000.

D.  

$552,000.

Discussion 0
Question # 29

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

Options:

A.  

263 CY

B.  

368 CM

C.  

201 CY

D.  

306 CY

Discussion 0
Question # 30

Which of the following is not an internal stakeholder?

Options:

A.  

Owner

B.  

installer

C.  

Subcontractor

D.  

Prime Contractor

Discussion 0

PSP PDF

PSP PDF (Printable)
$54.25
$154.99

PSP Testing Engine

PSP PDF (Printable)
$59.5
$169.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$74.55
$212.99

Free Exams Sample Questions