PSP Practice Questions

Planning & Scheduling Professional (PSP) Exam

Last Update 1 day ago
Total Questions : 216

Dive into our fully updated and stable PSP practice test platform, featuring all the latest Professional Level Certifications exam questions added this week. Our preparation tool is more than just a AACE International study aid; it's a strategic advantage.

Our free Professional Level Certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PSP. Use this test to pinpoint which areas you need to focus your study on.

PSP PDF

PSP PDF (Printable)
$43.75
$124.99

PSP Testing Engine

PSP PDF (Printable)
$50.75
$144.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$63.7
$181.99
Question # 21

What are Phases based on and derived from?

Options:

A.  

Resources

B.  

Constructability

C.  

Score of Work

D.  

Budget

Discussion 0
Question # 22

At the end of month one, did the delay to the parking structure foundation delay the project?

Options:

A.  

NO.

B.  

Yes, by 4 calendar days.

C.  

Yes, by 14 calendar days.

D.  

Yes, by 9 calendar days.

Discussion 0
Question # 23

What problems can a soils engineer deal with on a project?

Options:

A.  

Survey error.

B.  

Hidden subsurface conditions.

C.  

Archeological findings.

D.  

Toxic soils.

Discussion 0
Question # 24

Determine the correct formula and date for the late finish for Activity 2001.

Question # 24

Options:

A.  

L

F.  

2001 - 1 day -> 08-28-01.

B.  

LS.2002- 1 day-> 08-29-01.

C.  

LS.2002 + 1 day -> 08-30-01.

D.  

LS.2002 - 1 day -> 08-28-01.

Discussion 0
Question # 25

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.  

$289.000

B.  

$321.000

C.  

$193,000

D.  

$327,000

Discussion 0
Question # 26

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Options:

A.  

Is a milestone.

B.  

It is on the critical path.

C.  

Was completed in the past.

D.  

Has yet to be completed.

Discussion 0
Question # 27

When are KPIs defined?

Options:

A.  

At project initiation

B.  

At NTP

C.  

At the start of the Construction Phase

D.  

After the Bidding Phase

Discussion 0
Question # 28

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

Question # 28

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Question # 28

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.  

$420,000.

B.  

$307,000.

C.  

$524,000.

D.  

$552,000.

Discussion 0
Question # 29

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

Options:

A.  

263 CY

B.  

368 CM

C.  

201 CY

D.  

306 CY

Discussion 0
Question # 30

Which of the following is not an internal stakeholder?

Options:

A.  

Owner

B.  

installer

C.  

Subcontractor

D.  

Prime Contractor

Discussion 0