Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PSP Planning & Scheduling Professional (PSP) Exam is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PSP Practice Questions

Planning & Scheduling Professional (PSP) Exam

Last Update 1 day ago
Total Questions : 216

Dive into our fully updated and stable PSP practice test platform, featuring all the latest Professional Level Certifications exam questions added this week. Our preparation tool is more than just a AACE International study aid; it's a strategic advantage.

Our free Professional Level Certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PSP. Use this test to pinpoint which areas you need to focus your study on.

PSP PDF

PSP PDF (Printable)
$43.75
$124.99

PSP Testing Engine

PSP PDF (Printable)
$50.75
$144.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$63.7
$181.99
Question # 41

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

Options:

A.  

407 days

B.  

255 days

C.  

267 days

D.  

477 days

Discussion 0
Question # 42

What defines a KPI?

Options:

A.  

Phase milestones

B.  

Initiation of a weather risk window

C.  

Key discrete project final or interim goals

D.  

Interim milestones related to weather phasing

Discussion 0
Question # 43

How could the structural steel drawing delay have been prevented?

Options:

A.  

Add a time buffer at the end of structural steel activities.

B.  

Allow adequate time for review and resubmittal in the baseline schedule.

C.  

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.  

Switch to post-tensioned concrete construction.

Discussion 0
Question # 44

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.  

Subcontract outside forces to accelerate the Phase A Schedule

B.  

Allocating forces from other BILCO contracts to the toll road project

C.  

Proceeding with the work in advance of the environmental studies

D.  

Reduce the phasing from 5 phases to 3 phases

Discussion 0
Question # 45

The EBS is established by:

Options:

A.  

The contractor s planning and scheduling office

B.  

The government entity with the authority to approve/stop the work

C.  

The entity with the authority to fund and direct the enterprise

D.  

The contractors and subcontractors

Discussion 0
Question # 46

When should the project documents be reviewed to assess their impact on the organization and administration of a project?

Options:

A.  

After the Award and before the NTP

B.  

During the Bid Phase

C.  

Before the commercial decision to Did on the project

D.  

After the NTP

Discussion 0
Question # 47

A good change management plan___________.

Options:

A.  

is provided to stakeholders after it is created

B.  

is detailed during the planning phase

C.  

tracks minor decisions

D.  

involves only the project controls team

Discussion 0
Question # 48

Determine the correct formula and date for the late start for Activity 9001.

Question # 48

Options:

A.  

The early finish is required in order to determine the answer.

B.  

LS.6001 Dur.6001 -> 11-20-02.

C.  

There is insufficient data provided to calculate the answer.

D.  

L

F.  

9001 Dur.9001 -> 11-20-02.

Discussion 0
Question # 49

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

Question # 49

Options:

A.  

12-27-03 and 24 days of float

B.  

12-18-03 and 4 days of float

C.  

12-17-03 and 4 days of float

D.  

12-18-03 and 25 days of float

Discussion 0
Question # 50

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.  

Claims and disputes phase.

B.  

Installation phase.

C.  

Planning and design phase.

D.  

Turnover and start-up phase.

Discussion 0
Get PSP dumps and pass your exam in 24 hours!

Free Exams Sample Questions