PSP Practice Questions
Planning & Scheduling Professional (PSP) Exam
Last Update 1 day ago
Total Questions : 216
Dive into our fully updated and stable PSP practice test platform, featuring all the latest Professional Level Certifications exam questions added this week. Our preparation tool is more than just a AACE International study aid; it's a strategic advantage.
Our free Professional Level Certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PSP. Use this test to pinpoint which areas you need to focus your study on.
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

What day would Activity C complete if the duration of Activity A was reduced by five days?
Which of the following is NOT required when performing weekly or monthly schedule updates?
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:
The addition of which of the following relationships would cause a logic loop?
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
