PSP Planning & Scheduling Professional (PSP) Exam is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PSP Practice Questions

Planning & Scheduling Professional (PSP) Exam

Last Update 1 day ago
Total Questions : 216

Dive into our fully updated and stable PSP practice test platform, featuring all the latest Professional Level Certifications exam questions added this week. Our preparation tool is more than just a AACE International study aid; it's a strategic advantage.

Our free Professional Level Certifications practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PSP. Use this test to pinpoint which areas you need to focus your study on.

PSP PDF

PSP PDF (Printable)
$43.75
$124.99

PSP Testing Engine

PSP PDF (Printable)
$50.75
$144.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$63.7
$181.99
Question # 31

When are project planning and scheduling specifications established?

Options:

A.  

Before me NTP

B.  

Before the tendering documents are finalized

C.  

After the bid price is accepted

D.  

During the bidding process

Discussion 0
Question # 32

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

Question # 32

Options:

A.  

80 lifts

B.  

50 lifts

C.  

5 lifts

D.  

20 lifts

Discussion 0
Question # 33

What day would Activity C complete if the duration of Activity A was reduced by five days?

Options:

A.  

35

B.  

30

C.  

45

D.  

40

Discussion 0
Question # 34

The data date or status date of a schedule represents the:

Options:

A.  

date the monthly update is performed

B.  

date the project manager turns in the schedule update

C.  

system date when the software calculates the update

D.  

date on which progress is based

Discussion 0
Question # 35

Which of the following is NOT required when performing weekly or monthly schedule updates?

Options:

A.  

Percent complete.

B.  

Remaining duration of activities.

C.  

Actual finish of activities.

D.  

Original duration of activities.

Discussion 0
Question # 36

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.  

Not suitable for complicated projects with multiple planned critical paths.

B.  

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.  

Not suitable for projects with long durations.

D.  

Less accurate as the analysis advances through the project.

Discussion 0
Question # 37

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

Options:

A.  

1001 and 6001

B.  

1000. 1001. and 6001

C.  

9001 and 6002 and 6002

D.  

1000 and 6001

Discussion 0
Question # 38

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Options:

A.  

ahead of schedule

B.  

on schedule

C.  

complete

D.  

behind schedule

Discussion 0
Question # 39

The addition of which of the following relationships would cause a logic loop?

Options:

A.  

O H - D

B.  

O C - J

C.  

O F-I

D.  

O l-C

Discussion 0
Question # 40

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.  

Detailed listing of working days for each calendar used

B.  

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.  

Assigned party responsibility for each work task

D.  

Tabular listing of activities showing duration, calendar ID, early and late dates

Discussion 0