Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Planning & Scheduling Professional (PSP) Exam Practice Questions

Question # 61

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.  

Projected crew size

B.  

Estimated labor hours

C.  

Hours in a standard work day

D.  

Estimated cost

Discussion 0
Question # 62

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

Options:

A.  

Using the critical chain method

B.  

Fast tracking

C.  

Crashing

D.  

Rebaseline the project

Discussion 0
Question # 63

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.  

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.  

Replace the relationship from 'B’ to 'C’ with SSO

C.  

Reduce the duration of B" from 10 days to 5 days by compressing work effort

Discussion 0
Question # 64

NO: 98

The activity with the most total float is:

Question # 64

Options:

A.  

Activity I.

B.  

Activity

C.  

C.  

Activity

F.  

D.  

Activity

D.  

Discussion 0

PSP PDF

PSP PDF (Printable)
$54.25
$154.99

PSP Testing Engine

PSP PDF (Printable)
$59.5
$169.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$74.55
$212.99

Free Exams Sample Questions